U.S. Department of Energy			ORDER    
        Washington, D.C.			DOE O 412.1A

                             			Approved:  4-21-05
                     	

This directive was reviewed and certified as current and necessary by Susan J. Grant, Director, Office of Management, 
Budget and Evaluation/Chief Financial Officer, 4-21-05.


SUBJECT:	WORK AUTHORIZATION SYSTEM


1.	OBJECTIVES.  To establish a work authorization and control process for work 
performed by designated site and facility management contractors, and other contractors 
as determined by the procurement executive, consistent with the budget execution and 
program evaluation requirements of the Department of Energy’s (DOE’s) Planning, 
Programming, Budgeting, and Evaluation process.

2.	CANCELLATIONS.  DOE O 412.1 Work Authorization System, dated 4-20-99.  
Cancellation of a directive does not, by itself, modify or otherwise affect any contractual 
obligation to comply with such a directive.  Cancelled directives that are incorporated by 
reference in a contract remain in effect until the contract is modified to delete the 
references to the requirements in the cancelled directives.

3.	APPLICABILITY.

a.	Primary DOE Organizations, Including National Nuclear Security Administration 
(NNSA) Organizations.  Except for the exclusions in paragraph 3c, this Order 
applies to all Primary DOE Organizations that direct work to be performed by site 
and facility management contractors and other contractors determined by the 
procurement executive.  (See Attachment 1 for a complete list of Primary DOE 
Organizations.)  This Order automatically applies to Primary DOE Organizations 
created after it is issued.

The Administrator of NNSA shall assure that NNSA employees and contractors 
comply with their respective responsibilities under this Order.

b.	Site/Facility Management Contractors.  This Order will be applicable to 
contractors by provisions within the Department of Energy Acquisition 
Regulation (DEAR).

c.	Exclusions.

(1)	Facilities and activities of the NNSA Office of Naval Reactors and 
Bonneville Power Administration are excluded from the requirements of 
this Order.

(2)	Work involving reimbursable work for others and services, products, or 
materials regularly produced for sale at scheduled rates under DOE 
programs (e.g., routine irradiation services, radioisotopes, production or 
transmission of electricity) are excluded from the requirements of this 
Order.


4.	REQUIREMENTS.

a.	Authorizations and deauthorizations for all DOE funded work must be 
documented in work authorizations.  [Paperless generation and electronic transfer 
are preferred (see Attachment 2 for sample format).]

(1)	A program office may request a contractor to use a suggested standard 
work proposal (Attachment 3) to provide information for program 
planning, budget formulation, or documentation of part or all of a work 
assignment.
(2)	A site and facility management contractor may use a work proposal to 
propose work to a program office (see Attachment 3 for sample format). 

b.	At a minimum, each work authorization will contain the following information:
(1)	project title and reference to work proposal number, if applicable;
(2)	Headquarters programmatic point of contact, organization, and telephone 
number; 
(3)	Headquarters budget point of contact, organization code, and telephone 
number; 
(4)	responsible program; 
(5)	responsible program Secretarial Officer; 
(6)	responsible field organization;
(7)	responsible contracting officer if different from 4b(6) above;
(8)	site/facility management contractor name, point of contact, and telephone 
number; 
(9)	work authorization number (see paragraph 4c below), with revision 
number if applicable;
(10)	budget and reporting code and funding level; 
(11)	dates for performance period, work start, and work completion; 
(12)	statement of work (see paragraph 4d below);
(13)	reporting requirements, including (a) project management or status reports 
and (b) reports or publications for the purpose of informing DOE, the 
scientific community, and the public of the project results (e.g., scientific 
advances or technical progress); and
(14)	Headquarters, field organization, contractor, and if involving changes to 
scope, schedule, or funding, contracting officer signature blocks.

c.	Each work authorization must have a unique, standardized identification number, 
which must remain unchanged for the total life of the work assignment.

d.	The statement of work will include the following information as appropriate:

(1)	detailed statement of work to be performed or reference to a work 
proposal, project plan, or similar document describing the scope of work 
in detail;
(2)	required milestone dates;
(3)	deliverables, including technical information as required by DOE 
O 241.1A, Scientific and Technical Information Management, dated 
4-9-01; and
(4)	associated performance-based indicators/targets consistent with DOE 
G 120.1-5, Guidelines for Performance Measurement, dated 6-30-96, and 
any additional guidance that will assist the contractor in the performance 
of the work.

e.	DOE field organizations (contracting officers) must receive a work authorization 
signed by the appropriate Primary DOE Organization, who must review and 
approve the work as acceptable for the contractor before obligating funds for the 
contract.

(1)	Program offices may delegate some of the program managers’ 
responsibilities and authorities to DOE field organizations (e.g., 
assignment of tasks and/or distribution of funds to contractors under their 
cognizance).
(2)	When responsibilities have been delegated, the field organization is 
responsible for preparing and issuing the work authorization.

f.	A signed copy of each work authorization accepted by the contractor must be 
forwarded to DOE (preferably electronically) as evidence of acceptance of the 
authorized work.

(1)	If the authorization does not change scope, schedule, or cost (e.g., 
incremental funding), then contractor signatures are not necessary.  (Note, 
however, that if any changes are made, this information should still be 
forwarded to DOE as noted above.)
(2)	Work is not authorized to commence until the contractor receives both 
funding (via a signed contract modification) and the related work 
authorization.

g.	Funding guidance necessary to support work authorizations will be provided 
through the existing approved funding program (AFP) process.

(1)	The contractor retains the flexibility to manage individual tasks within the 
work assignment.
(2)	Manpower and dollars may be shifted, as necessary, subject to 
Government imposed constraints and program office direction.

h.	Authorizations for work planned in the current fiscal year are to be issued by the 
beginning of the fiscal year to the maximum extent possible.

(1)	Work authorizations should be transmitted to the field promptly following 
the issuance of the advice of allotment by the Office of Management, 
Budget and Evaluation.
(2)	Paperless generation and electronic transfer are preferred.

5.	RESPONSIBILITIES.

a.	Under Secretaries.  Establish DOE policy for assignment and control of work 
authorization for designated site and facility management contractors.

b.	Primary DOE Organizations.

(1)	Inform other DOE organizations of restrictions or constraints on the use of 
facilities under their cognizance.
(2)	Recommend to the cognizant Under Secretary appropriate changes in the 
policies for work authorization for designated site and facility management 
contractors.

c.	Program Secretarial Officers.

(1)	Provide general approval of work to be accomplished under the provisions 
of this Order, normally as part of institutional planning, budget 
formulation or execution, or similar processes.  (Approval of specific work 
authorizations and associated documentation may be delegated.)
(2)	Prepare work authorizations in accordance with paragraph 4, aggregating 
related work assignments at the highest appropriate level.
(3)	To the maximum extent possible, issue full annual funding and associated 
work authorizations to site and facility management contractors as early in 
the fiscal year as possible.
(4)	Ensure work to be assigned by work authorization—

(a)	is appropriate for performance by a contractor;
(b)	has clearly articulated requirements and technically and 
programmatically adequate documentation; and
(c)	will be performed in a manner compliant with the terms and 
conditions of the contract, including security and environmental, 
safety, and health (ES&H) requirements.

(5)	As needed, revise and issue work authorizations to DOE field 
organizations and request necessary AFP changes through the Chief 
Financial Officer in accordance with established procedures for 
administrative control of funds.
(6)	Transmit work authorizations to the field promptly after submission of the 
AFP to the Chief Financial Officer.
(7)	Ensure that formal agreement is reached with DOE field organizations 
anytime they are delegated technical assessment or technical oversight and 
control of work assignments.
(8)	Monitor performance and reports submitted by contractors, unless this 
function is delegated, to ensure contractors comply with all work 
requirements defined in their contracts, including the statement of work, 
reporting requirements, documentation, data, cost management, work 
products, milestone schedules and deliverables.

d.	DOE Field Organizations.

(1)	Ensure work to be assigned by work authorization—
(a)	is within the contracting officer’s representative’s (COR’s) 
delegated authority and
(b)	is not duplicative of other ongoing work under the contractor’s 
responsibility.
(2)	Ensure work performed by contractors does not violate constraints on use 
of DOE-controlled facilities and is carried out in a manner that protects the 
workers, the public, and the environment against ES&H hazards and 
safeguards and security risks arising from the performance of contract 
work.
(3)	Ensure work authorization requirements have been satisfied before 
authorization to proceed and that the contractor has a clear understanding 
of what is required by the sponsoring program office before work 
commences.
(4)	Review all work authorizations under their cognizance to ensure they are 
appropriate for performance; within mission; and for institutional plans as 
applicable, within scope and agreed to general levels of effort.
(5)	Issue and revise work authorizations for assigned work if the assignment 
decision has been delegated.
(6)	Ensure the contractor provides a signed copy of the work authorization and 
all required reports to Program Secretarial Officers as required.
(7)	Monitor performance and reports submitted by contractors to ensure that 
work performed and costs incurred conform to work authorizations issued.
(8)	Authorize work in accordance with the AFP, programmatic guidance, 
contract-specific COR appointment letters, and established procedures for 
administrative control of funds.
(9)	Ensure costs related to work authorizations can be adequately tracked 
before issuing authorizations.
(10)	Review work proposals prepared by contractors for consistency with 
program and other guidance.
(11)	Transmit work proposals, with any comments and recommendations, to 
program offices in accordance with program guidance and budget time 
frames issued by the Chief Financial Officer.
(12)	Ensure contractors provide technical information to the Director of 
Scientific and Technical Information in accordance with reference 7d 
below. 
(13)	Perform contract oversight activities in accordance with the 
contract-specific COR appointment letter.

e.	Office of Management, Budget and Evaluation.  Performs tasks of an accounting 
and budgetary nature associated with the process described in this Order such as 
issuing allotments, AFPs, and financial reports.

6.	DEFINITIONS.  Please refer to the DOE glossary on the Internet at 
http://www.directives.doe.gov/pdfs/doegeninfo/draft/glossary.pdf for definitions.

7.	REFERENCES.

a.	Title XXXII of P.L. 106-65, National Nuclear Security Administration Act, dated 
October 5, 1999, as amended.
b.	DOE G 120.1-5, Guidelines for Performance Measurement, dated 6-30-96, 
provides guidance on performance measurement in DOE.
c.	DOE O 130.1, Budget Formulation, dated 9-29-95, establishes policy provisions 
and defines roles and responsibilities of Departmental organizations and 
contractors participating in the Department’s annual budget formulation process.
d.	DOE O 135.1, Budget Execution—Funds Distribution and Control, dated 
9-30-95, describes DOE systems, policies, and assignment of requirements for 
control of the budget execution process.
e.	DOE O 241.1A, Scientific and Technical Information Management, dated 4-9-01, 
provides guidance concerning the reporting and dissemination of technical 
information.  Scientific and technical information resulting from work funded by 
DOE is to be made broadly available to the scientific community and the public, 
within appropriate adherence to statutorily mandated protections.
f.	DOE P 450.4, Safety Management System Policy, dated 10-15-96, provides for a 
formal process to plan, perform, assess, and improve the safe conduct of work.
g.	DOE P 450.5, Line Environment, Safety and Health Oversight, dated 6-26-97, 
provides policy for DOE line management oversight of ES&H.
h.	DOE O 452.1B, Nuclear Explosive and Weapon Surety Program, dated 8-6-01, 
establishes requirements and responsibilities for the DOE Nuclear Explosive and 
Weapon Surety Program to ensure adequate safety, security, and control of 
nuclear explosives and nuclear weapons. 
i.	DOE O 452.2B, Safety of Nuclear Explosive Operations, dated 8-7-01, establishes 
requirements and responsibilities for ensuring the safety of both routine and 
planned DOE nuclear explosive operations and associated activities and facilities.
j.	DOE O 452.4A, Security and Control of Nuclear Explosives and Nuclear 
Weapons, dated 12-17-01, establishes DOE, including NNSA, requirements and 
responsibilities to prevent the deliberate unauthorized use of U.S. nuclear 
explosives and U.S. nuclear weapons.
k.	DOE/NNSA Weapon Quality Policy (QC-1) Development and Production 
Manual Technical Business Practices.
l.	DOE O 470.1, Safeguards and Security Program, dated 9-28-95, provides 
requirements and responsibilities for the appropriate protection levels against 
unauthorized access; theft, diversion, loss of custody, or destruction of nuclear 
weapons or components; espionage; loss or theft of classified matter or 
Government property; and other hostile acts that impact national security, the 
health and safety of employees, the public, or the environment.
m.	DOE O 534.1B, Accounting, dated 1-6-03, establishes requirements for financial 
management of cash, advances, receivables, inventories, and investment of funds; 
accountability for plant and capital equipment; current and long-term liabilities; 
and accounting for equity revenues, collections, expenses, and reimbursable work 
performed by DOE on behalf of Federal and non-Federal entities.
 
8.	CONTACT.  For assistance, contact the Office of Procurement and Assistance 
Management, 202-586-8182.

					SAMUEL W. BODMAN
							Secretary of Energy


ATTACHMENT 1. PRIMARY DOE ORGANIZATIONS, AND BY AGREEMENT THE NATIONAL NUCLEAR SECURITY ADMINISTRTION, TO WHICH DOE O 412.1A IS APPLICABLE

Office of the Secretary
Office of the Chief Information Officer
Office of Civilian Radioactive Waste Management
Office of Congressional and Intergovernmental Affairs
Office of Counterintelligence
Departmental Representative to the Defense Nuclear Facilities Safety Board
Office of Economic Impact and Diversity
Office of Electricity and Energy Assurance
Office of Energy Efficiency and Renewable Energy
Energy Information Administration
Office of Environment, Safety and Health
Office of Environmental Management
Office of Fossil Energy 
Office of General Counsel
Office of Hearings and Appeals
Office of Independent Oversight and Performance Assurance
Office of Inspector General
Office of Intelligence
Office of Legacy Management
Office of Management, Budget and Evaluation/Chief Financial Officer
Office of Nuclear Energy, Science and Technology
Office of Policy and International Affairs
Office of Public Affairs
Office of Science
Secretary of Energy Advisory Board
Office of Security 
Office of Security and Safety Performance Assurance
Southeastern Power Administration
Southwestern Power Administration
Western Area Power Administration



ATTACHMENT 2. SAMPLE WORK AUTHORIZATION

[NOTE:  See PDF or Word version online for the following forms.]

U.S. DEPARTMENT OF ENERGY 
CONTRACT WORK AUTHORIZATION
1a.	Project Title:
1b.	Work Proposal Number (if applicable):
2.	Headquarters Program Point of Contact.
Name:
Organization Code:
Telephone No.:
3.	Headquarters Budget Point of Contact.
Name:
Organization Code:
Telephone No.:
4.	Responsible Program:
5.	Responsible Secretarial Officer:
6.	Responsible Field Organization:

7a.	Site and Facility Management Contractor:
7b.	Contractor Point of Contact.
Name:			               Telephone No.:
8.	Work Authorization Number:
9.	Revision Number:*
10.	Funds Authorized ($ in thousands).
Budget and Reporting Code:
Previous:
Change:
Current:
11.	Performance Period Covered by Funds.
12.	Work Start Date:
13.	Expected Completion Date:
From:			           To:
14.	Statement of Work:  
(Attach a detailed description of work to be performed or reference to a work proposal, project plan, or similar document that describes 
the scope of work, milestones, deliverables, performance measures/expectations.)
15.	Reporting Requirements (Status reports, scientific and technical information or similar):
16.	Work Authorization Program Official.
Name (typed):
Signature:
Date:
17.	DOE Field Organization Official.
Name (typed):
Signature:
Date:
18.	Contractor’s Authorized Representative.
Name (typed):
Signature:
Date:
19.	DOE Contracting Officer (or delegated representative).
Name (typed):
Signature:
Date:
*The revision number will consist of a 2-digit program identifier, 4-digit sequential number, and the last digit of the fiscal year.


ATTACHMENT 2. SAMPLE WORK PROPOSAL

U.S. DEPARTMENT OF ENERGY 
WORK PROPOSAL
1.	Work Proposal Number:		2.  Revision Number:		3.  Date Prepared:
4.	Work Proposal Title:			  5.  Budget and Reporting Code:
6.	Work Proposal Term:  Begin   ___________    End  ___________
7.	Name (Last, First, MI) and Phone Number		8.  Headquarters Organization: 
of the Headquarters Program Manager:	
9.	DOE Field Organization Work Proposal 	10.  DOE Field Organization: 
Reviewer:
11.	Contractor Work Proposal Manager:		12.  Contractor Name: 
13.	Proposal Description (Approach, Anticipated Benefits in 200 Words or Less):
14.	Contractor Work Proposal Manager:	15.  DOE Field Organization Official:
                         (Signature)	  (Date)		                       (Signature)			(Date)
16.	Detail Attachments:  (See Specific Attachments)
0a.	Facility Requirements	0g.	Future Accomplishments	0m.	ES&H Considerations
0b.	Publications	0h.	Relationships to Other Projects	0n.	Human/Animal Subjects
0c.	Purpose (mandatory)	0i.	NEPA Requirements	0o.	Security Requirements
0d.	Background	0j.	Milestones	0p.	Other (specify)
0e.	Approach	0k.	Deliverables	
0f.	Technical Progress	0l.	Performance Measures/
			Expectations



WORK PROPOSAL REQUIREMENTS FOR OPERATING/EQUIPMENT
OBLIGATIONS AND COSTS
CONTRACTOR NAME:
WORK PROPOSAL 
NO.:
REV. NO.:
DATE PREPARED:




Prior 
Years


BY -1


Budget Year (BY)


BY +1


BY +2

Total to 
Complete

17.  Staffing (staff years):

a.  Scientific
b.  Other Direct
c.  Total Direct.

Request

Authorized

18.  Operating Expense:

a.  Total Obligations
b.  Total Costs
19.  Equipment:

a.  Equipment Obligations
b.  Equipment Costs

20.  Milestone Schedule:
Proposed
Authorized
21.  Reporting Requirements (Description):

END OF FORMS

DOE WORK PROPOSAL INSTRUCTIONS 
(page 1 of 3)
A.  The two-page DOE (including NNSA) Work 
Proposal is optional but may be required by a 
program office for planning and budget 
formulation.  It may be used as all or part of the 
documentation of a Work Authorization.  The 
form may also be used by a site and facility 
management contractor to describe prospective 
work.  The form is intended to provide an 
overview of the effort, including each of the tasks 
necessary for project completion.  Proposals 
should be limited to a single project to allow 
reporting of costs, obligations, and other 
information.

B.  Page 1 of the form.

Item 1.  Enter a unique number for the proposal. 
The first two characters of this number are to 
signify the DOE organizational code used when 
assigning regular contract numbers, such as EM, 
SC, and DP.  The third character is to be the 
letter “W.”  The remaining four characters will 
be a unique sequential number assigned by the 
requesting organization.

Item 2.  If the initial proposal is changed, a 
revision is indicated by placing a number in this 
space, starting with the number “1” and 
proceeding in sequence.

Item 3.  The month, day, and year the form is 
prepared (e.g., 10/01/03).

Item 4.  A descriptive title of the work being 
proposed.

Item 5.  The Budget and Reporting (B&R) Code 
in accordance with the B&R Classification Codes 
set forth on the Chief Financial Officer home 
page, www.cfo.doe.gov.



Item 6.  The start and estimated completion dates 
of the proposal.  Use a two-number format for 
month, day, and year (e.g., 10/01/03).  For 
proposals initiated for an indefinite period of 
time, the completion date should be shown as 
“OPEN.”

Item 7.  When known, enter the name and phone 
number of the DOE/NNSA program manager 
responsible for the overall program.

Item 8.  The DOE/NNSA Headquarters office 
responsible for the overall program.

Item 9.  When known, enter the name and phone 
number of the DOE field organization individual 
responsible for reviewing the proposal.

Item 10.  The DOE field organization responsible 
for the work proposal.

Item 11.  When known, enter the name and phone 
number of the contractor individual responsible 
for the proposal.

Item 12.  Enter the name of the contractor 
responsible for the proposal.

Item 13.  A description of the proposal, in 
200 words or less, highlighting the purpose, 
approach, and anticipated benefits the proposal 
will provide in the program’s mission.

Item 14.  The signature of the contractor 
representative responsible for the proposal and 
the date are to be entered when the proposal is 
given to the reviewing official.

Item 15.  The signature of the reviewing official 
and the date are to be entered when the proposal 
is forwarded to the program manager. 

Item 16.  Detailed attachments are to be 
completed if they are necessary to understand or 
will enhance the proposal.  Any attachments 
accompanying the proposal should be indicated 
by checking the appropriate blocks.  Each 
attachment page should include the contractor 
name, the proposal number, and the date 
prepared.
a.  Facility Requirements.  If execution of the 
proposal requires the use of existing or approved 
facilities, briefly describe the required use and 
location, with associated gross square footage and 
impact on site utility services by fiscal year in 
which the proposal begins and each subsequent 
fiscal year during the anticipated life of the 
proposal.  Facility needs will be reviewed in 
context of overall site planning and utilization 
and expressed in terms of space function (e.g., 
office, storage space, site utilities)
b.  Publications.  List all publications pertaining 
to the proposal during the prior fiscal year.  
Provide the title or subject and planned date of 
publications of all topical reports over the life of 
the proposal.  Periodic progress reports are to be 
listed in this section.
c.  Purpose.  Provide the reasons for the proposal 
and the objectives that will accomplish the stated 
purpose.  Each objective should be the single 
highest level of measurable achievement that can 
serve as a criterion for measuring the success or 
failure of the proposal.
d.  Background.  Present a brief historical 
overview of the proposal or preview work or 
theories that have led to the proposal.
e.  Approach.  Explain the management controls 
and methodology that will be used to execute the 
proposal in all fiscal years.
f.  Technical Progress.  Attach the last Technical 
Progress Report if required by the program.  Also, 
describe the technical progress in BY-3 (the last 
complete fiscal year) and expected progress for 
BY-2, BY-1, and BY.
g.  Future Accomplishments.  Describe any 
anticipated benefits that will accrue in the future 
which are attributable to the proposal.
h.  Relationship to Other Projects.  Provide a 
description of any relationships, 
interrelationships, or dependencies which the 
proposal has with other known federally funded 
projects.
i.  NEPA Considerations.  In accordance with the 
National Environmental Policy Act of 1969, 
describe the long-term and short-term potential 
impacts and effects of the work package upon the 
ecosystem and NEPA documentation that must be 
prepared.
j.  Milestones (if applicable).  A detailed 
explanation of the milestones presented on the 
second page of the proposal (item 20) should be 
given.  For basic research, the only milestone may 
be the submission of a yearly progress report.
k.  Deliverables.  An itemized list of deliverables 
under the proposal excluding reports in item 21.
l.  Performance Measures and Expectations.  A 
description of the performance measures 
described as outcomes and the expectations for 
achieving those measures by which the success of 
the proposal will be measured.
m.  ES&H Considerations.  A description of the 
ES&H hazards arising from performance of the 
proposed work and mitigating actions to protect 
the workers, the public, and the environment.


n.  Human/Animal Subjects Research.  Briefly 
describe any anticipated human subjects or animal 
subjects research activity that may occur as part 
of the proposed work.

o.  Security Requirements.  Identification of 
applicable security requirements.

p.  Other.  Any other attachments should be 
specified in the space provided on the work 
package form.

C.  Page 2 of the Form—General.  Header 
information on this page should be filled in as it 
appears on page 1.  The “Authorized” column is 
not completed unless requested by the program 
when funds have been authorized.  The column 
heading designations on page 2 of the 
DOE/NNSA Work Proposal form are defined 
below.  The relationship between the fiscal years 
(FYs) and budget years (BYs) for which 
information is being provided is illustrated in the 
table below.

Prior Years.  For proposals related to projects, 
information for all prior years in which work was 
performed should be provided to allow 
calculation of total project cost and other 
information.  This column is optional and should 
only be completed when requested by the 
program in the program guidance.

Item 17.  Designate personnel staffing in 
full-time equivalent person-years.  Enter the 
numbers of scientific and other direct 
person-years for all columns.

Item 18.  Enter estimates for total obligations and 
total costs per year for all columns.  This should 
include inventories.

Item 19.  Enter estimates for total obligations and 
total costs per year for all columns for equipment 
directly related to the proposal.

Item 20.  Enter the titles of supporting tasks in 
the “Milestone Schedule” column.  Each task 
should be followed by the total obligations in 
thousands of dollars in the “Proposed BY” 
column.  The dates (MO/YR) on which the tasks 
are projected for start and completion should be 
entered in the “Proposed Schedule” columns and 
will be completed, if requested by the program 
manager, when funds have been authorized.  
Based on the allocation of funds, enter the dates 
for planned start and completion of the respective 
tasks when requested.

Item 21.  Enter all reporting required for the 
proposed work, including a description and 
frequency for each report.



CALENDAR YEAR THAT DOE PREPARED BUDGET (BY)
2000                    2001                2002                2003
			BY-3 FY 1999	FY 2000	FY 2001	FY 2002
			BY-2 FY 2000	FY 2001	FY 2002	FY 2003
			BY-1 FY 2001	FY 2002	FY 2003	FY 2004
			BY    FY 2002	FY 2003	FY 2004	FY 2005
2001                    2002                2003                2004
CALENDAR YEAR THE CONGRESS CONSIDERS BUDGET (BY)

AVAILABLE ONLINE AT:				INITIATED BY:
http://www.directives.doe.gov 	Office of Procurement and Assistance Management