The PDF version pdf file
Display Related Directives to this directive.
Display Reference Documents to this directive.

U.S. DEPARTMENT OF ENERGY						ORDER
    Washington, D.C.						   DOE O 413.3A

								        Approved: 7-28-06
								       
SUBJECT:  PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF
		CAPITAL ASSETS
		
1.	OBJECTIVES.

	a.	To provide the Department of Energy (DOE), including the National 
		Nuclear Security Administration, with project management direction for 
		the acquisition of capital assets with the goal of delivering projects 
		on schedule, within budget, and fully capable of meeting mission 
		performance, safeguards and security, and environmental, safety, and 
		health standards.

	b.	To implement Office of Management and Budget Circulars A-11 Part 
		7, A-123, A-127, and A-130.

	c.	To implement DOE P 413.1, Program and Project Management Policy 
		for the Planning, Programming, Budgeting, and Acquisition of Capital 
		Assets, dated 6?10-00. 

2.	CANCELLATIONS. 

	DOE O 413.3, Program and Project Management for the Acquisition of 
	Capital Assets, dated 10-13-00. Cancellation of an Order does not by 
	itself modify or otherwise affect any contractual obligation to comply 
	with the Order. Contractor Requirements Documents containing directive 
	requirements that have been applied to a contract remain in effect 
	until the contract is modified to eliminate or replace requirements 
	from canceled directives. 

	Further, DOE O 413.3A cancels Chapters 1 through 3 of DOE M 413.3-1, 
	Project Management for the Acquisition of Capital Assets, dated 3-28-
	03, and takes precedence over the Manual where conflicts exist.
	
3.	APPLICABILITY.

	a.	DOE Elements. 

		The requirements identified in this Order are mandatory for all DOE 
		Elements (unless identified in the exclusions paragraph), including the 
		National Nuclear Security Administration, for all capital asset 
		acquisition projects having a Total Project Cost or Environmental 
		Management Total Project Cost for Clean-Up Projects greater than or 
		equal to $20 Million (M). 
		
		The principles as set forth in this Order and Project Assessment and 
		Reporting System reporting requirements apply to all projects with a 
		Total Project Cost or Environmental Management Total Project Cost 
		greater than or equal to $5M. While all requirements are to be 
		addressed, the approach to meeting the requirements should be tailored 
		consistent with the risk, complexity, visibility, cost, safety, 
		security, and schedule of the project. All programs and projects shall 
		comply with applicable laws, regulations, Executive orders, and DOE 
		directives.
		
		The Under Secretary, National Nuclear Security Administration will 
		assure that National Nuclear Security Administration employees and 
		contractors comply with their respective responsibilities under this 
		directive. Any reference in this Order to the Program Secretarial 
		Officer is also applicable to the Deputy Administrator/Associate 
		Administrators, National Nuclear Security Administration.

	b.	DOE Contractors. 
	
		The Contractor Requirements Document, Attachment 2, identifies specific 
		requirements of this Order that will apply to management and operating 
		and other prime contracts that include the Contractor Requirements 
		Document. The Contractor Requirements Document must be included in 
		contracts making the contractor responsible for project execution at 
		DOE-owned or -leased facilities. 

	c.	Exclusions. 

		(1)	Naval Reactors, National Nuclear Security Administration is 
			excluded in accordance with Executive Order 12344 and P.L.106-65.
	
		(2)	Bonneville Power Administration is excluded in accordance with 
			Secretarial Delegation Order 00-033.00A, dated 09/27/2002. 
	
		(3)	Financial Assistance awards (grants and cooperative agreements), 
			which are covered under 10 CFR 600, are excluded.
	
4.	IMPLEMENTATION. DOE-STD-1189-2006 provides implementation 
	guidance for Hazard Category 1, 2, and 3 nuclear facilities safety 
	requirements. Implementation of this order for Hazard Category 1, 2, 
	and 3 nuclear facilities is delayed until six months after issuance of 
	the Standard. 

5.	REQUIREMENTS. Topics addressed in the following paragraphs are 
	accessible through links in the following topic list.

	a.	Project Management Principles. 

		Fundamental project management principles provide a framework for 
		successful project execution. The requirements set forth in this Order 
		are established to ensure adherence to the following principles: 
	
		(1)	Line management accountability

		(2)	Sound disciplined up-front planning

		(3)	Development and implementation of sound acquisition strategies

		(4)	Well-defined and managed performance baselines

		(5)	Effective project management systems (e.g., quality assurance, 
			risk management, change control, performance management)

		(6)	Implementation of an Integrated Safety Management System

		(7)	Effective communication among all project stakeholders

	b.	DOE Acquisition Management System. 

		The DOE Acquisition Management System establishes principles and 
		processes to translate user needs and technological opportunities into 
		reliable and sustainable facilities, systems, and assets that provide a 
		required mission capability. The system is organized by project phases 
		and Critical Decisions (CDs), which represent a logical maturing of 
		broadly stated mission needs into well-defined requirements resulting 
		in operationally effective, suitable, and affordable facilities, 
		systems, and other products. Tailoring is an essential element of the 
		acquisition process and shall be applied to all projects, although the 
		greatest amount of tailoring will typically be applied to smaller, low-
		risk, and non-complex projects. Figure 1 illustrates a typical 
		implementation of the DOE Acquisition Management System for Line Item 
		Projects. 
	
	c.	Project Phases. 

		(1)	Initiation Phase. 

	During this phase, preconceptual planning activities focus on the 
	Program’s strategic goals and objectives. User needs are analyzed for 
	consistency with the Department’s strategic plan, Congressional 
	direction, administration initiatives, and political and legal issues. 
	One outcome of the analysis could be a determination that a user need 
	exists that cannot be met through other than material means. This 
	outcome leads to the development and approval of a Mission Need 
	Statement. The information developed during this phase also provides 
	the basis for the Project Engineering and Design budget request when 
	preliminary design activities are planned. 
	

Figure 1. Typical DOE Acquisition Management System for Line Item 
Projects.

		(1)	Definition Phase. 
	
			Upon approval of mission need, the project enters the Definition Phase 
			where alternative concepts, based on user requirements, risks, costs, 
			and other constraints, are analyzed to arrive at a recommended 
			alternative. This is accomplished using Systems Engineering and other 
			techniques and tools such as alternatives analysis and Value 
			Management/Value Engineering. This ensures the recommended alternative 
			provides the essential functions and capability at optimum life cycle 
			cost, consistent with required performance, scope, schedule, cost, 
			security, and Environment, Safety and Health considerations. During 
			this phase, the required Value Management assessment is completed, and 
			more detailed planning is accomplished which further defines required 
			capabilities. The products produced by this planning provide the detail 
			necessary to develop a range of estimates for the project cost and 
			schedule.
	
		(2)	Execution Phase. 

			Following the Definition Phase, preliminary design activities mark the 
			beginning of the Execution Phase. Systems Engineering continues to 
			balance requirements, cost, schedule, and other factors to optimize the 
			design, cost, and capabilities that satisfy the mission need. 
			Engineering and design continue until the project has a sufficiently 
			mature design that can be implemented successfully within a firm 
			Performance Baseline. 
	
			During this phase, the initial design concepts and the preliminary 
			design are developed into detailed and final designs and plans. These 
			plans are used to procure or manufacture components, fabricate 
			subsystems, or construct, remediate, decommission or demolish 
			facilities. Major activities in this phase include:

			(a)	Establishing Performance Measurement Baselines and implementing 
			change control procedures;

			(b)	Satisfying environmental and safety requirements;

			(c)	Obtaining approved National Environmental Policy Act 
			documentation, if required, prior to the start of detail or final 
			design;

			(d)	Continuing to refine and optimize cost estimates, schedules, and 
			designs; and

			(e)	Approving the final design for procurement and implementation. 

			(f)	Identifying and addressing security concerns.

			Execution comprises the longest and most costly phase of a project. 
			Value Management and Value Engineering are implemented throughout the 
			project Execution Phase to ensure the most effective solutions are 
			implemented. 
			
			If the delivery method is Design-Build versus Design-Bid-Build and a 
			single contract is awarded for both design and construction, it may be 
			necessary to tailor the project’s execution process to allow the 
			project team to propose cost-effective innovative approaches that 
			reduce project duration and cost.
			
		(3)	Transition/Closeout Phase. 

			When the project nears completion and has progressed into formal 
			transition and commissioning, which generally includes final testing, 
			inspection, and documentation, the project is prepared for operation, 
			long?term care, or closeout. The nature of the transition and its 
			timing depends on the type of project and the requirements that were 
			identified subsequent to the mission need. 

	b.	Critical Decisions. 

		The five Critical Decisions are major milestones approved by the 
		Secretarial Acquisition Executive or Acquisition Executive that 
		establish the mission need, recommended alternative, Acquisition 
		Strategy, the Performance Baseline, and other essential elements 
		required to ensure that the project meets applicable mission, design, 
		security, and safety requirements. Each Critical Decision marks an 
		increase in commitment of resources by the Department and requires 
		successful completion of the preceding phase or Critical Decision. 
		Collectively, the Critical Decisions affirm the following:

		·	There is a need that cannot be met through other than material 
			means;
		
		·	The selected alternative and approach is the optimum solution;
		
		·	Definitive scope, schedule and cost baselines have been 
			developed;
		
		·	The project is ready for implementation; and
		
		·	The project is ready for turnover or transition to operations.
		
		The amount of time between decisions will vary. Projects may quickly 
		proceed through the early Critical Decisions due to a lack of 
		complexity, the presence of constraints that reduce available 
		alternatives, or the absence of significant technology and 
		developmental requirements. In these cases, more than one Critical 
		Decision may be approved simultaneously. Conversely, there may be a 
		need to split a Critical Decision. 
		
		(1)	CD-0, Approve Mission Need. 

			The Initiation Phase begins with the identification of a mission-
			related need. A Program identifies a credible performance gap between 
			its current capabilities and capacities and those required to achieve 
			the goals articulated in its strategic plan and/or in the DOE Target 
			Enterprise Architecture for IT capital asset projects.. A Mission Need 
			Statement is the translation of this gap into functional requirements 
			that cannot be met through other than material means. It should 
			describe the general parameters of the project, how it fits within the 
			mission of the Program, and why it is critical to the overall 
			accomplishment of the Department mission, including the benefits to be 
			realized. The mission need is independent of a particular solution, and 
			should not be defined by equipment, facility, technological solution, 
			or physical end-item. This approach allows the Program the flexibility 
			to explore a variety of solutions and not limit potential solutions. 
			Approval of CD-0 formally establishes a project and begins the process 
			of conceptual planning and design used to develop alternative concepts 
			and functional requirements. Additionally, CD-0 approval allows the 
			Program to request Project Engineering and Design funds for use in 
			preliminary design, final design, and baseline development.

		(2)	CD-1, Approve Alternative Selection and Cost Range. 

			CD-1 approval marks the completion of the project Definition Phase, 
			during which time the conceptual design is developed. This is an 
			iterative process to define, analyze, and refine project concepts and 
			alternatives. This process uses a systems methodology that integrates 
			requirements analysis, risk identification and analysis, acquisition 
			strategies, and concept exploration to evolve a cost-effective, 
			preferred solution to meet a mission need. Approval of CD-1 provides 
			the authorization to begin the project Execution Phase and allows 
			Project Engineering and Design funds to be used. For design-build 
			projects, Project Engineering and Design funds may be used to develop a 
			Statement of Work/Request for Proposal. Additionally, long-lead 
			procurements may be approved during this phase, provided National 
			Environmental Policy Act documentation is prepared, where applicable.
			
		(3)	CD-2, Approve Performance Baseline. 

			Completion of preliminary design is the first major milestone in the 
			project Execution Phase. Preliminary design is complete when it 
			provides sufficient information for development of the Performance 
			Baseline in support of CD-2. The Performance Baseline is developed 
			based on a mature design, a well-defined and documented scope, a 
			resource-loaded detailed schedule, a definitive cost estimate, and 
			defined Key Performance Parameters. Approval of CD-2 authorizes 
			submission of a budget request for the total project cost. For projects 
			with design periods less than 18 months, a budget request may be 
			submitted prior to CD-2 approval as part of tailoring.

		(4)	CD-3, Approve Start of Construction. 

			With design and engineering essentially complete, a final design review 
			performed, all environmental and safety criteria met, and all security 
			concerns addressed, the project is ready to begin construction, 
			implementation, procurement, or fabrication. CD-3 provides 
			authorization to complete all procurement and construction and/or 
			implementation activities and initiate all acceptance and turnover 
			activities. Approval of CD-3 authorizes the project to commit all the 
			resources necessary, within the funds provided, to execute the project.
			
		(5)	CD-4, Approve Start of Operations or Project Completion. 

			CD-4 marks the achievement of the completion criteria defined in the 
			Project Execution Plan and approval of transition to operations. This 
			decision is predicated on the readiness to operate and/or maintain the 
			system, facility, or capability. Transition and turnover does not 
			necessarily terminate all project activity. Rather, it marks a point at 
			which the operations organizations assume responsibility for operation 
			and maintenance. All projects must have a project transition/closeout 
			plan that clearly defines the basis for attaining initial or full 
			operating capability or meeting performance criteria as required for 
			project closeout, as applicable. The key attributes in turnover are the 
			Government’s readiness to operate, the ability to assume operational 
			responsibility, and the acceptance of the asset.
			
	c.	Critical Decision Approval Authority and Thresholds. 

		The Deputy Secretary serves as the Secretarial Acquisition Executive 
		for the Department and promulgates Department-wide policy and 
		direction. The Critical Decision authorities, thresholds and 
		delegations are identified in Table 1.
		
		·	Major System Projects. 
		
			Projects with a Total Project Cost greater than or equal to $750M or 
			Environmental Management Clean-Up Projects with an Environmental 
			Management Total Project Cost of $1B are Major System Projects. All 
			Major System Project Critical Decisions must be proposed by the 
			appropriate Program Secretarial Officer and approved by the Deputy 
			Secretary as DOE’s designated Secretarial Acquisition Executive before 
			proceeding to the next project phase or Critical Decision.

		·	Non-Major System Projects. 

			Projects with a Total Project Cost less than $750M or Environmental 
			Management Clean-Up Projects with an Environmental Management Total 
			Project Cost less than $1B are Non-Major System Projects. The 
			designated Acquisition Executive must approve all Non-Major System 
			Project Critical Decisions, except for CD?0, which cannot be delegated 
			below the Program Secretarial Officer.

		The Chief Information Officer will function as the Acquisition 
		Executive for all Information Technology capital assets deemed by the 
		Deputy Secretary to be Department-wide with total project Development, 
		Modernization, and Enhancement funding of $20 M and greater, and 
		Development, Modernization, and Enhancement funding of $5 M or more in 
		Current year or Budget year. Departmental Information Technology 
		capital assets will be defined by the Deputy Secretary and are 
		characterized by: 1) their widespread and continuous use among multiple 
		Departmental organizational units; 2) their vital importance to 
		accomplishing the Department’s business functions; and 3) their special 
		importance to agency senior management.

		Table 1. Critical Decision Authority Thresholds

See tables and figures in the PDF.

		Table 2 provides a list of mandatory prerequisites to obtain 
		Secretarial Acquisition Executive/Acquisition Executive approval for 
		each Critical Decision. Additionally, Table 2 provides approval 
		authorities. Where no approval authorities are noted, authorities are 
		established through other directives or the Programs (e.g., Functions 
		and Requirements Assignment Matrix). Any reference in this Table to the 
		Program Secretarial Officer is also applicable to the Deputy 
		Administrator/Associate Administrators, National Nuclear Security 
		Administration. Appropriate to project risk, size, and complexity, 
		requirements are expected to be tailored to the project and be approved 
		by the Secretarial Acquisition Executive/Acquisition Executive. 
		Projects must utilize the five Critical Decisions; however, in unique 
		circumstances, Critical Decisions may be combined or split by 
		appropriate tailoring. The tailoring approach must have a rational, 
		clear, and documented basis. DOE-STD-1189-2006 provides implementation 
		guidance for Hazard Category 1, 2, and 3 nuclear facilities safety 
		requirements.

		Table 2. Critical Decision Requirements
See tables and figures in the PDF.

 
CD Requirements 	   

Order 413.3A Requirements*	Approval Authority	   

CD-0 Requirements 		   

Perform Pre-conceptual Planning activities that focus on the Program’s 
strategic goals and objectives, safety planning, and design. 		   

Prepare a Mission Need Statement that documents a mission requirement 
that cannot be met through other than material means. Additionally, the 
Mission Need Statement will document the potential hazards and their 
safety, security, and risk implications.	Program Secretarial Officer 
(with recommendation from Program Analysis and Evaluation for projects 
with a Total Project Cost or Environmental Management Total Project 
Cost > $100M)	   

Prepare a Tailoring Strategy, if required, that describes the project’s 
approach for appropriately adapting Critical Decision requirements 
based on the project’s risk and complexity. The Tailoring Strategy may 
be included in the Project Execution Plan at later Critical Decisions.
	Secretarial Acquisition Executive or Acquisition Executive	   

Perform a Mission Validation Independent Project Review on all Major 
System Projects. 	Program Secretarial Officer	   

Prepare a Program Requirements Document (for National Nuclear Security 
Administration only) that defines the ultimate goals which the project 
must satisfy.		   

Evaluate projects for Information Technology elements within the 
Departmental Enterprise Architecture framework.	Chief Information 
Officer for Departmental Information Technology capital assets with 
Development Modernization Enhancements funding > or equal to $5M in 
Current Year or Budget Year, or Development Modernization Enhancements 
funding > or equal to $20M.	   

CD-1 Requirements 		   

Prepare a Conceptual Design Report which is an integrated systems 
engineering effort that results in a clear and concise definition of 
the project. 		 

Prepare an Acquisition Strategy that describes the high-level business 
and technical management approach designed to achieve project 
objectives within specified resource constraints. 	Program 
Secretarial Officer (with recommendation from the Office of Engineering 
and Construction Management for Major System Projects). 	   

Comply with the One-for-One Replacement legislation (excess 
space/offset requirement) as mandated in House Report 109-86.		   

Prepare a preliminary Project Execution Plan, including a Risk 
Management Plan and Risk Assessment, that establishes the initial 
policy and procedures to be followed to manage and control project 
execution.	Secretarial Acquisition Executive or Acquisition Executive 	   

Approve appointment of the Federal Project Director. 	Secretarial 
Acquisition Executive or Acquisition Executive (with Program Manager 
recommendation)	   

Establish and charter an Integrated Project Team. An Integrated Project 
Team, led by the Federal Project Director, is a multi-disciplinary 
team, which includes safety expertise. The Charter includes membership, 
roles and responsibilities, decision making authority and operating 
guidance. The Charter may be included in the Project Execution Plan.
	
Secretarial Acquisition Executive or Acquisition Executive 	   

Conduct a Design Review of the conceptual design. Design Reviews are 
performed to determine if a product (drawings, analyses, or 
specifications) is correct and will perform its intended functions and 
meet requirements. 

As part of the Design Review, for high-risk, high-hazard, and Hazard 
Category 1, 2, and 3 nuclear facilities, conduct a Technical 
Independent Project Review, the focus of which is to determine that the 
safety documentation is sufficiently conservative and bounding to be 
relied upon for the next phase of the project.

For Information Technology projects, the design review is a review of 
the preliminary System Description Document.		   

Prepare a Project Data Sheet for Line Item Projects to request Project 
Engineering and Design funds for preliminary and final design.		   

Approve Long-Lead Procurements, if necessary. 	Secretarial Acquisition 
Executive or Acquisition Executive	   

Implement Integrated Safety Management into management and work process 
planning at all levels per DOE P 226.1.		   

Prepare environmental documents including National Environmental Policy 
Act strategy and analyses, and permit applications.		   

Document High Performance Sustainable Building considerations, also 
referred to as “sustainable environmental stewardship” per DOE O 450.1, 
chg 2, is documented in the Conceptual Design Report and Acquisition 
Strategy, as appropriate.		 

Prepare a Preliminary Security Vulnerability Assessment Report as 
defined in DOE M 470.4-1.		   

Prepare an Initial Cyber Security Plan for Information Technology 
projects in accordance with DOE O 205.1.		   

Prepare a Conceptual Safety Design Report for Hazard Category 1, 2, and 
3 nuclear facilities. 		   

Prepare a Preliminary Hazard Analysis Report for facilities that are 
below Hazard Category 3 threshold as defined in 10 CFR 830, Subpart B 
and obtain DOE approval (field level). 		   

Prepare a Preliminary Safety Validation Report on the DOE review of the 
Conceptual Safety Design Report for Hazard Category 1, 2, and 3 nuclear 
facilities.		   

Determine that the Quality Assurance Program is acceptable and 
continues to apply. The Quality Assurance Program must fully address 
all applicable Quality Assurance Criteria as defined in 10 CFR 830 
Subpart A and DOE O 414.1C.		   

CD-2 Requirements		   

Establish a Performance Baseline to include Key Performance Parameters, 
total project cost, schedule and scope. The key project milestones and 
completion date shall be stated no less specific than month and year. 
The scope will be stated in quantity, size and other parameters that 
give shape and form to the project. The Performance Baseline may be 
included in the Project Execution Plan.	Secretarial Acquisition 
Executive approves Performance Baselines for Major System Projects, 
Acquisition Executive for Non-Major System Projects. For performance 
baseline deviation approvals, see Section 5.i. Baseline Management	   

Update the Project Execution Plan to incorporate changes resulting from 
the design effort in all areas including design considerations, 
performance baseline, risk analysis, project management, configuration 
management, and roles and responsibilities. 	Secretarial Acquisition 
Executive or Acquisition Executive	   

Employ an Earned Value Management System that is compliant with 
ANSI/EIA-748-A-1998 for projects with a Total Project Cost or 
Environmental Management Total Project Cost greater than or equal to 
$20M. Projects having a Total Project Cost or Environmental Management 
Total Project Cost between $20M and $50M must have an Earned Value 
Management System that is self-certified by the contractor as ANSI/EIA-
748-A-1998 compliant. Projects having a Total Project Cost or 
Environmental Management Total Project Cost greater than or equal to 
$50M require an ANSI/EIA-748-A-1998 compliant system certified by the 
Office of Engineering and Construction Management. For projects not 
required to utilize an Earned Value Management System (e.g., firm 
fixed-price contract projects), an alternative performance management 
system must be described in the Project Execution Plan.	Secretarial 
Acquisition Executive/Acquisition Executive for Alternative Performance 
Management System 	 

Perform a Performance Baseline Validation External Independent Review 
or a Performance Baseline Validation Independent Project Review. 
External Independent Reviews are conducted by the Office of Engineering 
and Construction Management to validate the Performance Baseline for 
projects with a Total Project Cost or Environmental Management Total 
Project Cost greater than or equal to $100M. Independent Project 
Reviews are conducted by the Project Management Support Office to 
validate the Performance Baseline for projects with a Total Project 
Cost or Environmental Management Total Project Cost less than $100 M.

The Office of Engineering and Construction Management for 
projects with a Total Project Cost or Environmental Management Total 
Project Cost ³ $100M, The Project Management Support Office for 
projects with a Total Project Cost or Environmental Management Total 
Project Cost < $100M must issue a Performance Baseline Validation 
Letter to the Program Secretarial Officer that describes the cost, 
schedule, and scope being validated.	   

Develop an Independent Cost Estimate or perform an Independent Cost 
Review for Major System Projects as part of the Performance Baseline 
Validation External Independent Review performed by the Office of 
Engineering and Construction Management. An Independent Cost Estimate 
should be performed where complexity, risk, cost, or other factors 
create a significant cost exposure for the Department. 		   

Determine that the Quality Assurance Program is acceptable and 
continues to apply. The Quality Assurance Program must fully address 
all applicable Quality Assurance Criteria as defined in 10 CFR 830 
Subpart A and DOE O 414.1C. 		   

Prepare a Preliminary Design. This stage of the design is complete when 
it provides sufficient information to support development of the 
Performance Baseline. 		   

Update the Project Data Sheet, if applicable.		   

Conduct a Design Review of the preliminary design. Design Reviews are 
performed to determine if a product (drawings, analyses, or 
specifications) is correct and will perform its intended functions and 
meet requirements. 

For nuclear facilities, design reviews should include a focus on safety 
and security systems. 

For Information Technology projects, the design review is a review of 
the updated System Description Document. 		   

Prepare a Preliminary Safety Design Report based on the Conceptual 
Safety Design Report for Hazard Category 1, 2, and 3 nuclear 
facilities. 		   

Prepare a Hazard Analysis Report by updating the Preliminary Hazard 
Analysis Report based on new hazards and design information and obtain 
DOE approval (field level). 		   

Update the Preliminary Security Vulnerability Assessment Report.		   

Update the Initial Cyber Security Plan for Information Technology 
projects.		 

Prepare a Preliminary Safety Validation Report based on DOE review of 
the Preliminary Safety Design Report for Hazard Category 1, 2, and 3 
nuclear facilities.		   

Incorporate Preliminary Sustainable Environmental Stewardship-High 
Performance Sustainable Building provisions into the preliminary design 
and design review.		   

Complete (or obtain approval of) final National Environmental Policy 
Act documentation, which must be completed prior to the start of final 
design.		   

CD-3 Requirements		   

Complete and review Final Design or determine that the design is 
sufficiently mature to start procurement or construction. 

For Information Technology projects, the Final Design review is a 
review of the final System Description Document. 		   

Update all CD-2 project documentation and required approvals to reflect 
any changes resulting from final Design, including the Project 
Execution Plan, Performance Baseline, Project Data Sheet, etc.

Various: See prior approvals	   

Perform an External Independent Review for Construction or Execution 
Readiness. An External Independent Review is performed by the Office of 
Engineering and Construction Management on all Major System Projects to 
verify execution readiness. A similar Independent Project Review must 
be performed by the appropriate Program Secretarial Office for Non-
Major System Projects unless justification is provided and a waiver is 
granted by the Acquisition Executive.		   

Prepare the Preliminary Documented Safety Analysis Report based on the 
Preliminary Safety Design Report for Hazard Category 1, 2, and 3 
nuclear facilities. 		   

Update the Hazard Analysis Report and obtain DOE approval (field 
level).		   

Update the Preliminary Security Vulnerability Assessment Report.		   

Update the Cyber Security Plan for Information Technology projects.	
	   
Prepare a Safety Evaluation Report based on review of the Preliminary 
Documented Safety Analysis for Hazard Category 1, 2, and 3 nuclear 
facilities.		   

Prepare a Construction Project Safety and Health Plan** and obtain DOE 
approval (field level).		   

Incorporate Final Sustainable Environmental Stewardship-High 
Performance Sustainable Building provisions into the Final Design and 
the External Independent Review.		 

Update the Quality Assurance Program for construction, field design 
changes, and procurement activities.		   

CD-4 Requirements		   

Verify Key Performance Parameters or Project Completion Criteria have 
been met and mission requirements achieved.		   

Complete a Readiness Assessment or an Operational Readiness Review and 
resolve all pre-start findings including ensuring Operations and 
Maintenance Staff are properly trained and qualified to operate and 
maintain the equipment, systems, and facilities being turned over.	

Issue a Checkout, Testing, and Commissioning Plan** that identifies 
subtasks, systems, and equipment. The Commissioning Plan ensures that 
the equipment, systems, and facilities including High Performance 
Sustainable Building systems, perform as designed and are optimized for 
greatest energy efficiency, resource conservation, and occupant 
satisfaction. The Commissioning Plan includes checkout and testing 
criteria required for initial operations. 		   

Issue a Project Transition to Operations Plan** that clearly defines 
the basis for attaining initial operating capability, full operating 
capability, or project closeout, as applicable. The plan includes 
documentation, training, interfaces, and draft schedules.		   

Issue an updated Quality Assurance Plan to address testing, identified 
deficiencies, and startup, transition, and operation activities.		   

Revise the environmental management system to ensure that it 
incorporates new environmental aspects related to turnover and 
operations		   

Prepare the Documented Safety Analysis Report with Technical Safety 
Requirements for Hazard Category 1, 2, and 3 nuclear facilities.		   

Update the Construction Project Safety and Health Plan**		   

Finalize the Hazard Analysis Report and obtain DOE approval (field 
level).		   

Finalize the Security Vulnerability Assessment Report.		   

Finalize the Cyber Security Plan for Information Technology projects 
and complete the Certification and Accreditation, as required.		   

Prepare a Safety Evaluation Report based on a review of the Preliminary 
Documented Safety Analysis for Category 1, 2, and 3 nuclear facilities.	
	 
Post CD-4 Requirements 		   

Perform final administrative and financial closeout and prepare a Final 
Project Closeout Report once all project costs are incurred and 
invoiced and all contracts are closed. The report includes final cost 
details as required (including claims and claims settlement strategy 
where appropriate).		   

Prepare a Lessons Learned Report and submit to OECM for broader sharing 
among the DOE project management community.		   

Complete project required Operational Documentation.		   

Conduct Post Implementation Review for Information Technology projects 
and document that the project has attained the desired results and met 
the Key Performance Parameters in accordance with the Capital 
Programming Guide, Supplement to Part 7 of the Office of Management and 
Budget’s Circular A-11.		   

*   Documents and reports are not intended to be stand-alone and may be 
combined.

** Not applicable to Clean-Up Projects. See DOE M 413.3-1 for 
additional Environmental Management Clean-Up Project guidance.	 

	d.	Tailoring. 

		Tailoring is an essential element of the acquisition process and must 
		be appropriate considering the risk, complexity, visibility, cost, 
		safety, security, and schedule of the project. The requirements of this 
		Order are to be applied on a tailored basis as appropriate to the 
		project. Tailoring is subject to the Acquisition Executive’s approval 
		and is identified prior to the impacted Critical Decision and approved 
		as early as possible starting at CD-0, if appropriate. In the Tailoring 
		Strategy or the Project Execution Plan, the Federal Project Director 
		will identify those areas a project plans to tailor and an 
		explanation/discussion of each tailored area. The Project Execution 
		Plan/Tailoring Strategy is updated prior to each Critical Decision 
		request. Tailoring does not imply the omission of essential elements in 
		the acquisition process that are necessary for all projects, or other 
		processes that are appropriate to a specific project’s requirements or 
		conditions. Moreover, concerning matters relating to integrating safety 
		into the early design of a facility, it is not anticipated that 
		tailoring or modification of the acquisition process would be 
		desirable. Details concerning the application of tailoring are provided 
		in DOE M 413.3-1.

	e.	Application of Critical Decisions to Unique Projects. 

		Although most DOE projects will follow the outlined Critical Decision 
		process, there are some unique project situations where customizing the 
		process is beneficial, such as the following:

		(1)	Environmental Management Cleanup Projects. 

			These projects include Environmental Clean-up work, Environmental 
			Management Clean-Up Projects, and Environmental Restoration projects. 
			These “projects” could include hundreds of release sites at the lowest 
			level, that are aggregated into Environmental Protection Agency 
			regulated Operable Units or Performance Baseline Summaries. These are 
			further aggregated into a total site-wide program. Decontamination and 
			decommissioning activities may also be aggregated in the same manner. 
			Other projects may range from a single project for a closure site, to 
			disposition of a waste stream, to a grouping of similar work activities 
			or geographic locations within a large site. See DOE M 413.3-1 for 
			additional Environmental Management Clean-Up Project guidance.

		(2)	Information Technology Projects. 

			Departmental Information Technology capital assets will be defined by 
			the Deputy Secretary and are characterized by: 1) their widespread and 
			continuous use among multiple Departmental organizational units; 2) 
			their vital importance to accomplishing the Department’s business 
			functions; and 3) their special importance to Agency senior management. 
			Information Technology projects are not meant to encompass process or 
			control systems that are an integral part to a broader project. 
			Additionally, this policy is applicable to commercial-off-the-shelf 
			acquisitions.

			The DOE Critical Decision process is normally tailored for Information 
			Technology projects to provide sufficient flexibility during the phased 
			or spiral approach required for these projects. Generally, system 
			design and development using a combined CD-2/3 process is required to 
			support various procurement alternatives and software/firmware 
			implementation in lieu of conventional construction. This tailored 
			approach does not reduce or eliminate management, performance to 
			baselines or technical requirements. The Federal Project Director uses 
			this framework to guide development of documentation to plan, manage, 
			and execute the project and designate appropriate design approvals at 
			the Integrated Project Team level. 

		(3)	Design-Build Projects. 

			Design-Build is a project delivery method where a single contract is 
			awarded for both design and construction. Design-Build can be used most 
			successfully with projects that have well-defined requirements, are not 
			complex, and have limited risks. This applies to projects that have few 
			“unknowns” or new technology requirements, little to no program or 
			system integration, and are not unique or first-of-a-kind. Projects 
			such as road building, administrative facilities, fire stations, and/or 
			replication of previously accomplished projects are generally the most 
			appropriate for design-build consideration. The Design-Build approach 
			requires the development of a functional design and clearly stated 
			operating requirements that provide sufficient information to allow 
			prospective contractors to prepare bids or proposals, but also allows 
			them the flexibility to implement innovative design and construction 
			approaches, value engineering, and other cost and time savings 
			initiatives. This overall objective of the Design-Build approach is to 
			reduce the total cost to the government and deliver projects more 
			quickly than the traditional Design-Bid-Build approach.

			Projects for which Design-Build is an appropriate delivery method will 
			generally have clear and well-defined requirements early in the 
			process. Accordingly, at the time of CD-0, much of the cost and 
			schedule information is known along with key design criteria. For such 
			projects, CD-0 and CD-1 may be accomplished simultaneously. 
			Essentially, in requesting a simultaneous approval CD-0 and CD-1, the 
			Integrated Project Team is asserting that:

			·	There is no advantage to the government of further evaluation of 
			alternatives;
			
			·	The project functions and requirements are well known; and
			
			·	A reasonable cost and schedule range can be established.

			In some instances, design-build projects may be managed in a close-
			coupled or fast-track fashion, whereby the initiation of facility 
			construction precedes the development of detailed facility design, 
			e.g., construction begins during the preliminary design stage of a 
			project. In these cases, the project's technical risks are typically 
			much more significant than for a traditional design and construction 
			approach. To address potential complications, aggressive risk 
			mitigation strategies are required to address the unique 
			characteristics of close-coupled or fast-track design-build projects. 
			Risk management strategies must be outlined in the risk management plan 
			and at a minimum address: (1) all technical uncertainties, (2) the 
			establishment of design margins to address the unique nature of the 
			design, and (3) increased technical oversight requirements.
			
			Approval of CD-0 and CD-1 establishes Design-Build as the project 
			delivery method and allows the project to go forward with development 
			of sufficient design work to establish the Performance Baseline and 
			solicitation package. Because of the maturity of the requirements, the 
			lack of complexity, and the cost and schedule knowledge gained from 
			similar efforts, establishing the Performance Baseline may be 
			expedited. In most cases, CD-3 may be requested simultaneously with CD-
			2. A tailored External Independent Review would be accomplished to 
			support validation of the Performance Baseline.

			Design-Build projects generally will not use Project Engineering and 
			Design funds. The Project Data Sheet must be submitted for the budget 
			year in which the Design-Build contract is to be awarded and must 
			include the costs of design as part of the Total Project Cost. The 
			program office may budget for Project Engineering and Design funds if 
			there is a need to develop significant performance or technical 
			specifications for the project.

		(4)	Projects Requiring Long-lead Procurement. 

			For particular projects, including those requiring long-lead 
			procurement or major equipment items, it may be necessary to split CD-2 
			and/or -3. For example, long-lead procurement might constrain 
			construction, and an early or phased CD-3 could be initiated and 
			justified. While there is potential risk in procuring equipment before 
			the design is complete, the potential schedule improvement may be 
			significant and more than compensate for the risk. The need to phase or 
			segment CD-3 should not be confused with minor, early activities that 
			are necessary and generally performed prior to CD-3. Activities such as 
			site characterization, limited access, safety, and security issues 
			(i.e., fences, etc.) are often necessary prior to CD-3, and may be 
			pursued as long as funding approvals are in place. If an early or 
			phased CD-3 is anticipated, the need for this decision and the process 
			is normally documented in the Project Execution Plan/Tailoring 
			Strategy.

		(5)	Projects Authorized by the Annual National Defense Authorization 
			Acts.

			The following are requirements from Title 50 United States Code for 
			projects authorized by the annual National Defense Authorization Acts:
			
			(a)	The Secretary shall submit a request for funds for a conceptual 
				design for a project if the estimated cost of the conceptual design 
				exceeds $3 million. 

			(b)	The conceptual design for a project shall be completed before 
				requesting funds for a construction project. 

			(c)	If the Total Estimated Cost for construction design for a project 
				exceeds $600,000, funds for that design must be specifically authorized 
				by law. 

			(d)	Construction on a project may not be started if the current Total 
				Estimated Cost of the project exceeds by more that 25% the amount shown 
				in the most recent data sheet submitted to Congress.
			
			This is only a sampling of the more common unique projects that may 
			require tailoring of the Critical Decision process or project phases. 
			Therefore, rather than accommodate these as exceptions, guidance is 
			provided in DOE M 413.3-1.

	f.	Reviews. 

		Reviews are an important project activity and must be planned as an 
		integral part of the project and tailored appropriate to project risk, 
		complexity, duration, and Critical Decision or phase. The following is 
		a summary of key reviews organized by Critical Decision.
		
		(1)	CD-0. 

			(a)	Mission Validation Independent Project Review. 

				A Mission Validation Independent Project Review is a limited review 
				prior to CD-0 for Major System projects. It validates the mission need 
				and the cost range. A Value Study may also be conducted, as 
				appropriate, to assist in CD-0.

		(b)	Mission Need Statement Review. 

				The Office of Program Analysis and Evaluation within the Office of the 
				Chief Financial Officer will review the Mission Need Statement and 
				provide a recommendation to the Program Secretarial Officer for 
				projects with a Total Project Cost or Environmental Management Total 
				Project Cost greater than or equal to $100M.

		(2)	CD-1. 

			(a)	Acquisition Strategy Review. Acquisition Strategies for Major 
				System Projects must be sent to the Energy Systems Acquisition Advisory 
				Board Secretariat for review by the Office of Engineering and 
				Construction Management prior to scheduling CD-1 decisional briefings. 
				The Federal Program Manager, Federal Project Director and Contracting 
				Officer must concur with the Acquisition Strategy prior to the Office 
				of Engineering and Construction Management review. The Office of 
				Engineering and Construction Management will provide a recommendation 
				to the appropriate Program Secretarial Officer or Deputy/Associate 
				Administrator who holds approval authority. Approval of the Acquisition 
				Strategy does not constitute approval required by the Offices of 
				Procurement and Assistance Management (DOE or National Nuclear Security 
				Administration, as applicable) for specific contract clearance 
				purposes, including contract acquisition plans. 

			(b)	Technical Independent Project Review. Prior to CD-1 approval, the 
				Program Secretarial Officer will perform a Technical Independent 
				Project Review to ensure safety and security is effectively integrated 
				into design and construction for high risk, high hazard, and Hazard 
				Category 1, 2, and 3 nuclear facilities. The review should ensure 
				safety documentation is complete, accurate, and reliable for entry into 
				the next phase of the project.

			(c)	Design Reviews. Design Reviews are an integral part of a project. 
				Beginning at CD-1 and continuing through the life of the project, as 
				appropriate, Design Reviews are performed by individuals external to 
				the project. Design Reviews are performed to determine if a product 
				(drawings, analysis, or specifications) is correct and will perform its 
				intended functions and meet requirements. Design Reviews must be 
				conducted for all projects and must involve a formalized, structured 
				approach to ensure the reviews are comprehensive, objective, and 
				documented.

		(3)	CD-2. 

			Performance Baseline Validation Review. A Performance Baseline 
			Validation Review is required to provide reasonable assurance that the 
			project can be successfully executed. Independent Project Reviews are 
			required to validate the Performance Baseline for projects with a Total 
			Project Cost or Environmental Management Total Project Cost less than 
			$100M. The Acquisition Executive may request an External Independent 
			Review in lieu of an Independent Project Review through the Office of 
			Engineering and Construction Management, and must do so if the 
			Acquisition Executive has no Project Management Support Office to 
			perform the review. For all projects with a Total Project Cost or 
			Environmental Management Total Project Cost greater than or equal to 
			$100M, the Office of Engineering and Construction Management utilizes 
			the external independent review in support of the performance baseline 
			validation. As part of the External Independent Review, either an 
			Independent Cost Estimate or Independent Cost Review is employed. 

		(4)	CD-3. 

			Construction or Execution Readiness Review. An External Independent 
			Readiness Review must be performed by the Office of Engineering and 
			Construction Management on Major System Projects to verify execution 
			readiness. At a minimum, this review verifies the readiness of the 
			project to proceed into construction or remedial action. The findings 
			of the Execution Readiness Review and any corrective actions must be 
			presented to the Secretarial Acquisition Executive as a part of CD-3 
			approval. A similar Independent Project Review may be performed by the 
			appropriate Program Secretarial Officer for Non-Major System Projects 
			as requested by the Acquisition Executive.

		(5)	CD-4. 

			Operational Readiness Review or Readiness Assessment. As appropriate, 
			an Operational Readiness Review or Readiness Assessment is conducted 
			prior to approving CD-4. 
			
	g.	Baseline Management. 

		(1)	Performance Baseline Deviation. 

			A Performance Baseline deviation occurs when the approved cost, 
			schedule, performance, or scope parameters cannot be met. The Federal 
			Project Director must ensure management is promptly notified whenever 
			the project performance indicates the likelihood of a Performance 
			Baseline deviation. When a deviation occurs, the approving authority 
			must make a specific determination whether to terminate the project or 
			establish a new Performance Baseline. The Secretarial Acquisition 
			Executive must approve Performance Baseline changes under any of the 
			following circumstances for Projects: 
			
			·	An increase in excess of the lesser of $25M or 25% (cumulative) 
				of the original CD-2 cost baseline.
			
			·	A delay of six-months or greater (cumulative) from the original 
				project completion date.

			·	A change in scope that affects the ability to satisfy the mission 
				need, an inability to meet a Key Performance Parameter, or non-
				conformance with the current approved Project Execution Plan, which 
				must be reflected in the Project Data Sheet.
			
			The Secretarial Acquisition Executive must approve Performance Baseline 
			changes under any of the following circumstances for Clean-Up Projects: 
			
			·	An increase in excess of the lesser of $100M or 25% (cumulative) 
				of the original CD-2 Environmental Management Total Project Cost 
				baseline.
			
			·	A delay of one year or greater (cumulative) from the original 
				project completion date.
			
			·	Any change in scope that affects the site end-state.
			
			The Under Secretaries for Projects and the Program Secretarial Officer 
			for Environmental Management Clean-Up Projects are the approval 
			authorities for Performance Baseline changes below Secretarial 
			Acquisition Executive approval level. These approval authorities may be 
			delegated to the Program Secretarial Officers or below. New Performance 
			Baseline approval thresholds and authorities should be documented in 
			the Project Execution Plan for project changes below the thresholds 
			identified above. Additionally, all Performance Baseline deviation 
			decisions must be reported to the Secretarial Acquisition Executive. 
			These approval levels must be incorporated into the change control 
			process for each project. New performance baselines to be established 
			because of a deviation must be validated by the Office of Engineering 
			and Construction Management for projects with a Total Project Cost or 
			Environmental Management Total Project Cost greater than or equal to 
			$100M and by the Project Management Support Office for projects with a 
			Total Project Cost or Environmental Management Total Project Cost less 
			than $100M. 

		(2)	Directed Changes. 

			Project changes caused by DOE Policy Directive, Regulatory, or 
			Statutory action, such as changes in approved budget or the addition of 
			new requirements are to be called Directed Changes. Directed changes 
			follow the appropriate baseline management process.
			
		(3)	Change Control. 

			Change control ensures that project changes are identified, evaluated, 
			coordinated, controlled, reviewed, approved/disapproved, and documented 
			in a manner that best serves the project. The change control process is 
			defined in the Project Execution Plan. One key goal of change control 
			is to ensure Performance Baseline thresholds are not exceeded. Changes 
			can be classified into two broad categories: those that impact the 
			Performance Baseline and those that do not. Approval authority for 
			changes depends upon the impact of the change and can range from the 
			contractor to the Secretarial Acquisition Executive, usually with the 
			involvement and support of a Change Control Board. Significant changes 
			could require Congressional notification. Additional information 
			concerning change control is provided in DOE M 413.3-1.
			
	h.	Project Reporting and Progress Reviews. 

		Monthly project status must be reported using the web-based Project 
		Assessment and Reporting System. Approval of CD-0 initiates a 
		requirement for project status reporting which continues through the 
		approval of CD-4 for all projects with a Total Project Cost or 
		Environmental Management Total Project Cost greater than or equal to 
		$5M. Additionally, the Acquisition Executive or designee must begin 
		holding quarterly progress reviews. The requirement for quarterly 
		reviews cannot be delegated below the Acquisition Executive for Non-
		Major System Projects. The Secretarial Acquisition Executive may 
		delegate quarterly reviews for Major System Projects to the Under 
		Secretaries. For Environmental Management Clean-Up Projects, quarterly 
		reviews may be delegated to the Program Secretarial Officer. The Office 
		of Engineering and Construction Management must be invited to quarterly 
		reviews for all projects with a Total Project Cost greater than or 
		equal to $100M.

		At CD-2 and continuing through CD-4, critical performance information 
		must be reported in the Project Assessment and Reporting System. 
		Projects having a Total Project Cost or Environmental Management Total 
		Project Cost greater than or equal to $20M must report Earned Value 
		performance. All projects with a Total Project Cost or Environmental 
		Management Total Project Cost greater than or equal to $5M require, at 
		a minimum, the input of Key Performance Parameters, key milestones and 
		a project performance assessment (Green, Yellow, or Red) as determined 
		by the:

		·	Federal Project Director for projects having a Total Project Cost 
			greater than or equal to $5M and less than $20M (or up to $100M for 
			Environmental Management Clean-Up projects);
		
		·	Program Secretarial Officer for Projects having a Total Project 
			Cost greater than or equal to $20M and less than $100M (see above 
			bullet for Environmental Management Clean-Up projects);
		
		·	Program Secretarial Officer for Environmental Management Clean-Up 
			Projects having a Total Project Cost greater than $100M and less than 
			or equal to $400M; and
		
		·	The Office of Engineering and Construction Management for 
			Projects having a Total Project Cost greater than or equal to $100M and 
			Environmental Management Clean-Up Projects having an Total Project Cost 
			greater than $400M. 
		
		Project performance assessment is determined using the following 
		criteria:

		·	Green – Project is expected to meet its cost, schedule, and 
			Performance Baseline.
		
		·	Yellow – Project is at risk of breaching its cost, schedule, and 
			Performance Baseline.
		
		·	Red – Project is expected to breach its cost, schedule, and 
			Performance Baseline.

	i.	Topical Areas.

		(1)	Acquisition Strategy. 

			An acquisition strategy is a high-level description of a business and 
			technical management approach designed to achieve project objectives 
			within specified resource constraints. The acquisition strategy conveys 
			the Integrated Project Team’s approach for the successful acquisition 
			of the project, its intended outcomes, and rationale for that approach. 
			This document is a CD-1 requirement and is the framework for planning, 
			organizing, staffing, controlling, and leading a project. Key elements 
			of an Acquisition Strategy are provided in DOE M 413.3-1.

		(2)	Conceptual Design/Conceptual Design Report.

			Following approval of CD-0, Approval of Mission Need, the project team 
			will commence development of the alternative strategies that will 
			satisfy the Mission Requirements identified in the Program Requirements 
			Document. These alternative strategies will culminate in the proposed 
			path forward for the project, the Conceptual Design. The activities 
			that support the development of the Conceptual Design are funded 
			through the Program Office and these costs will eventually be collected 
			and included in the project’s Total Project Cost. Title 50 U.S. Code 
			for Projects authorized by annual National Defense Authorization Acts 
			requires that any time during the development of the Conceptual Design 
			or the Conceptual Design Report the cost will exceed the $3M 
			notification threshold, Congress must be officially notified. Until the 
			approval of CD-1, Approval of Preliminary Baseline Range, there is no 
			capital funding authorized for the project, i.e., all funds expended 
			will be Program funds. In view of the Congressional notification 
			requirement, the project must keep track of the costs that are allowed 
			for the Conceptual Design.

			The specific information that is included in the Conceptual Design and 
			the allowable and prohibited costs are identified in DOE M 413.3. As a 
			minimum, the Conceptual Design should develop the following: the scope 
			required to satisfy the Program Mission requirements, the project 
			feasibility and attainment of specified performance levels, reliable 
			cost and schedule range estimates, project criteria and design 
			parameters, and identification of requirements and features. 
			
		(3)	Earned Value Management System. 

			An Earned Value Management System is the integrated set of policies, 
			processes, procedures, systems, and practices that meet the intent of 
			the guidelines identified in ANSI/EIA-748-A-1998. This system is 
			generally documented by a system description and procedures that 
			translate the Earned Value Management Policy into specific 
			organizational approaches of how the 32 guidelines in ANSI/EIA-748-A-
			1998 will be executed. For projects executed under firm fixed price 
			contracts or level of effort contracts, the Secretarial Acquisition 
			Executive/Acquisition Executive may approve an alternative performance 
			management system. The Earned Value Management System or alternative 
			performance management system is described in the Project Execution 
			Plan. A complete description of the Earned Value Management System 
			capabilities are provided in ANSI/EIA-748-A-1998 and is discussed in 
			the DOE M 413.3-1.

		(4)	Environment, Safety and Health Documentation Development. 

			At CD-1, for Hazard Category 1, 2, and 3 nuclear projects, a Conceptual 
			Safety Design Report is developed to:
			
			(a)	Document and establish a preliminary inventory of hazardous 
				materials, including radioactive materials and chemicals; 
			
			(b)	Document and establish the preliminary hazard categorization of 
				the facility; 
			
			(c)	Identify and analyze primary facility hazards and facility Design 
				Basis Accidents; 
			
			(d)	Provide an initial determination, based on preliminary hazard 
				analysis, of Safety Class and Safety Significant Structures, Systems, 
				and Components; 
			
			(e)	Include a preliminary assessment of the appropriate Seismic 
				Design Category for the facility itself as well as Safety Significant 
				Structures, Systems, and Components; 
			
			(f)	Evaluate the security hazards that can impact the facility safety 
				basis (if applicable); and 
				
			(g)	Include a commitment to the nuclear safety design criteria of DOE 
				O 420.1 (or proposed alternative criteria). 
			
			At CD-2, a Preliminary Safety Design Report is developed from the 
			Conceptual Safety Design Report to reflect more refined analyses based 
			on the evolving design and safety integration activities during 
			preliminary design. The Preliminary Safety Design Report should include 
			the results of process hazards analyses and confirm or adjust, as 
			appropriate, the items included in the Conceptual Safety Design Report. 

			At CD-3, a Preliminary Documented Safety Analysis Report is prepared 
			and updates the safety information in the Preliminary Safety Design 
			Report and identifies and justifies changes from the design approach 
			described in the Preliminary Safety Design Report. At CD-4, a 
			Documented Safety Analysis Report is developed based on information 
			from the Preliminary Documented Safety Analysis Report and the Safety 
			Evaluation Report. Technical Safety Requirements are developed to 
			document and establish specific parameters and requisite actions for 
			safe facility operation. DOE-STD-1189-2006 provides the technical 
			guidance on the preparation of nuclear facility safety documents.
			
			For CD-1, projects involving facilities that are below Hazard Category 
			3 threshold as defined in 10 CFR 830, Subpart B, must prepare a 
			Preliminary Hazard Analysis Report to identify and evaluate all 
			potential hazards and establish a preliminary set of safety controls. 
			Hazardous chemicals are analyzed in accordance with Integrated Safety 
			Management requirements (DOE P 450.4), 29 CFR 1910.119, Process Safety 
			Management of Highly Hazardous Chemicals, and 40 CFR 68, Chemical 
			Accident Prevention Provisions. For CD-2, a Hazard Analysis Report is 
			developed by updating the Preliminary Hazard Analysis Report to include 
			any new or revised information on facility hazards and safety design. 
			For CD-3 and -4, hazard analysis and controls are updated in the Hazard 
			Analysis Report 

			All projects must comply with environmental protection requirements 
			including National Environmental Policy Act documentation, anticipated 
			permitting requirements, and cost-effective environmental stewardship-
			high performance sustainable building principles. A Construction 
			Project Safety and Health Plan is prepared prior to construction 
			activities per 10 CFR 851 Appendix A. paragraph 1(d). An Operational 
			Readiness Review or Readiness Assessment is conducted for Hazard 
			Category 1, 2, and 3 nuclear projects in accordance to DOE O 425.1C. 
			The Program Secretarial Officer will need to determine what level of 
			readiness review is needed for projects involving facilities that are 
			below Hazard Category 3 threshold.
			
		(5)	Integrated Project Team. 

			The Integrated Project Team, organized and led by the Federal Project 
			Director, is an essential element in DOE’s acquisition process and is 
			used during all phases of a project’s life cycle. This team consists of 
			professionals representing diverse disciplines with the specific 
			knowledge, skills, and abilities to support the Federal Project 
			Director in successfully executing a project. The team membership will 
			change as a project progresses from initiation to closeout to ensure 
			the necessary skills are always represented to meet project needs. Team 
			membership may be full or part time, depending upon the scope and 
			complexity of a project. The Federal Project Director and the team will 
			prepare and maintain a Team Charter that describes: 
			
			(a)	membership; 

			(b)	responsibilities and authority; 

			(c)	leads (as appropriate); 

			(d)	meetings; 

			(e)	reporting; and 

			(f)	operating guidance. 

			Additional information on Integrated Project Teams is provided in DOE M 
			413.3-1.

		(6)	Integrated Safety Management System. 

			The Department is committed to performing all work so missions can be 
			accomplished with adequate controls in place to protect the public, 
			workers, and the environment. The fundamental premise of Integrated 
			Safety Management System is that accidents are preventable through 
			early and close attention to planning, design, and physical execution 
			of a project. The Integrated Safety Management System is designed to 
			ensure that safety is appropriately addressed throughout the life cycle 
			of a project. Identification of potential hazards must begin early in 
			project planning and continue throughout the life cycle of the project. 
			DOE policy requires safety management systems be used to systematically 
			integrate safety into management and work processes at all levels. The 
			Integrated Safety Management System is characterized by DOE’s 
			expectation that project management will effectively implement seven 
			guiding principles: 

			(a)	Line management responsibility for safety; 

			(b)	Clear roles and responsibilities; 

			(c)	Competence commensurate with responsibility; 

			(d)	Balanced priorities; 

			(e)	The Conceptual Safety Design Report must identify safety 
				standards and requirements to include preliminary seismic design 
				category for the facility itself as well as Safety Class and Safety 
				Significant Structures, Systems, and Components;

			(f)	Engineered controls tailored to the functions being designed or 
				performed; and

			(g)	Approval to proceed. 

				Tailoring is to be applied to a project’s Integrated Safety Management 
				System to enable tasks to be managed at the appropriate levels. In 
				effect, management systems function to optimize task planning and 
				performance to enable those closest to the task plan to assume 
				responsibility. Additional Integrated Safety Management System 
				information is provided in DOE M 413.3-1 and the OECM, Project 
				Management Practices, Integrated Safety, Revision E, June 2003. This 
				document defines the five Integrated Safety Management core functions:
			
			(h)	Define work scope;

			(i)	Analyze hazards;

			(j)	Establish and implement controls;

			(k)	Perform work/design; and 

			(l)	Provide feedback and improvement.

		(7)	Key Performance Parameters. 

			A Key Performance Parameter is a vital characteristic of the project or 
			facility mission. It is a characteristic, function, requirement, or 
			design basis that if changed would have a major impact on the system or 
			facility performance, schedule, cost, and/or risk; or, the ability of 
			an interfacing project to meet its mission requirements. They could be 
			applicable either to the overall system/facility level as a whole 
			and/or to one or more major subsystems. Parameters that are appropriate 
			for Key Performance Parameters are those that express performance in 
			terms of accuracy, capacity, throughput, quantity, processing rates, 
			purity, or others that define how well a system, facility, or other 
			type of project will perform. Additional details concerning the 
			application of Key Performance Parameters are provided in DOE M 413.3-
			1.

		(8)	Performance Baseline. 

			The Performance Baseline, as established in the Project Execution Plan, 
			defines the cost, schedule, performance, and scope commitment to which 
			the Department must execute a project. When the development effort has 
			reached a phase where the requirements and design are mature and the 
			uncertainty and risks have been eliminated, reduced, mitigated, or 
			accepted a project is able to establish the parameters within which it 
			will be executed. These key parameters, when completely identified, 
			define the Performance Baseline. The Performance Baseline includes the 
			entire project budget (total cost of the project including contingency) 
			and represents DOE’s commitment to the Congress and the Office of 
			Management and Budget. The Performance Baseline must be controlled, 
			tracked, and reported from the beginning to the end of a project to 
			ensure consistency between the Project Execution Plan, the Project Data 
			Sheet, and the Exhibit 300 (a requirement of Office of Management and 
			Budget Circular A-11, Part 7). 

		(9)	Project Execution Plan. 

			The Project Execution Plan is the core document for management of a 
			project. The Federal Project Director is responsible for the 
			preparation of this document. It establishes the policies and 
			procedures to be followed to manage and control project planning, 
			initiation, definition, execution, and transition/closeout, and uses 
			the outcomes and outputs from all project planning processes, 
			integrating them into a formally approved document. A Project Execution 
			Plan includes an accurate reflection of how the project is to be 
			accomplished, resource requirements, technical considerations, risk 
			management, configuration management, and roles and responsibilities. A 
			preliminary Project Execution Plan is required to support CD-1. This 
			document continues to be refined throughout a project’s life cycle and 
			revisions are documented through the configuration management process. 
			Key elements of a Project Execution Plan are provided in DOE M 413.3-1. 
			
		(10)	Quality Assurance. 

			Quality Assurance begins at project inception and continues through the 
			project’s life cycle. The Federal Project Director is responsible for 
			planning and implementing a Quality Assurance Program for the project. 
			Quality affects cost, availability, effectiveness, safety, and 
			performance. Appropriate aspects of Quality Assurance need to be 
			considered during the preparation of project documents. The project’s 
			application of Quality Assurance is documented in either the 
			organizational or project-specific Quality Assurance Program that 
			addresses 10 basic criteria: program, personnel training and 
			qualification, quality improvement, documents and records, work 
			processes, design, procurement, inspection and acceptance, management 
			access, and independent assessment. The key requirements/elements of a 
			Quality Assurance Program are provided in DOE O 414.1C and 10 CFR 830 
			Subpart A.

		(11)	Risk Management. 

			Risk Management is an essential element of every project. The DOE risk 
			management approach must be analytical, forward looking, structured, 
			informative, and continuous. Risk assessments are started as early in 
			the project life cycle as possible and should identify critical 
			technical, performance, schedule, and cost risks. Once risks are 
			identified, sound risk mitigation strategies and actions are developed 
			and documented. As a project progresses, new information improves 
			additional insight into risk areas and allows the continuous refinement 
			of the risk mitigation strategies. A close relationship between the 
			Integrated Project Team and the contractor promotes better 
			understanding of program risks and assists in developing and handling 
			project risks. Additional risk management information is provided in 
			DOE M 413.3-1.

		(12)	Safeguards and Security. 

			Safeguards and security refers to an integrated system of activities, 
			systems, programs, facilities, and policies for the protection of 
			classified information and/or classified matter, unclassified control 
			information, nuclear materials, nuclear weapons, nuclear weapon 
			components, and/or the Department’s and its contractors’ facilities, 
			property, and equipment. 
			
			In order to support overall project planning and design, applicable 
			safeguards and security requirements must be identified at the earliest 
			possible project phase. Project success will depend upon the 
			satisfaction of safeguards and security requirements. Using the 
			preliminary safeguards and security plans developed in the previous 
			phase and the increasing maturity of program planning will allow 
			project personnel to determine that all safeguards and security 
			requirements can be met and are appropriately factored into project 
			cost and schedule.
			
			Following the identification of applicable safeguards and security 
			requirements, their potential impact on mission objectives; 
			satisfaction of environment, safety, and health requirements; and other 
			aspects of the project must be evaluated. Preliminary identification of 
			alternatives (including facility design and the incorporation of 
			safeguards and security technologies) must be made and these 
			alternatives evaluated with respect to their impact on mission needs, 
			satisfaction of other requirements (such as safety requirements), and 
			other cost effectiveness. The applicable safeguards and security 
			requirements, the alternatives considered in the first project phase, 
			and the preliminary approach to satisfying safeguards and security 
			requirements must be documents and this documentation should be 
			reviewed as part of CD-0. This input becomes part of the conceptual 
			design requirements for further development.

			Identification of potential security risks must begin early in project 
			planning as part of implementing Integrated Safeguards and Security 
			Management. DOE P 470.1 requires safeguards and security management 
			systems be used to systematically integrate security into management 
			and work practices at all levels. Approval authorities of the 
			safeguards and security documents are prepared according to DOE M 
			470.4-1. Starting with CD-1 and continuing through CD-3, for safeguards 
			Category I, II, and III, nuclear material assets are identified and 
			vulnerability and risk assessments are performed. The Security 
			Vulnerability Assessment Report, developed in CD-1 and updated in 
			subsequent CDs, describes the methodologies used in vulnerability 
			analyses, sets forth supporting information used, provides the results 
			of vulnerability analyses and risk assessments, and establishes risk 
			ratings. A security plan is developed and submitted to DOE for 
			approval.

			Identification of potential sources of elevated safeguards and security 
			risk and/or avoidable safeguards and security costs must begin early in 
			project planning and continue as project planning and design efforts 
			proceed. DOE P 470.1 requires that a balance must be achieved among 
			safeguards and security, programmatic, and operational considerations 
			and that safeguards and security strategy must be tailored to the work 
			being performed to mitigate risk. Achievement of this balance and the 
			tailoring of safeguards and security strategy within capital projects 
			is best accomplished through the systematic application of security 
			expertise operating in conjunction with the project management system. 
			To that end, the preliminary assessment of potential safeguards and 
			security concerns and alternatives developed prior to CD-0 must 
			continue and the results be documented as the project matures. A 
			critical review of the integration of safeguards and security into the 
			overall project plan and design must be included as a portion of the 
			CD-1 decision process. 

			Prior to CD-2, the set of applicable safeguards and security 
			requirements, the methods selected to satisfy those requirements, and 
			any potential risk acceptance issues must be reviewed and validated as 
			complete and accurate. During the CD-2 decision process, the Project 
			Execution Plan and the Performance Baseline must be reviewed to ensure 
			that cost, schedule, and integration aspects of safeguards and security 
			are appropriately addressed, that all feasible risk mitigation has been 
			identified, and that the safeguards and security concerns for which 
			explicit line management risk acceptance will be required are 
			appropriately supported. 

2.	KEY ROLES AND RESPONSIBILITIES. 

	Three themes regarding roles and responsibilities necessary to achieve 
	defined project objectives as well as the objectives of this Order 
	include:

	·	Strengthening line management accountability for successful 
		project management results;
	
	·	Clearly defining the roles, responsibilities, authority, and 
		accountability of the Federal Project Management Team relative to the 
		contractor Project Management Team; and
	
	·	Developing effective Integrated Project Teams to assist the 
		Federal Project Director in planning, programming, budgeting, and 
		successfully acquiring capital assets.
	
	Line managers are responsible for successfully developing, executing, 
	and managing projects within the approved Performance Baseline. 
	Delegation of authority from one line manager to a lower-level line 
	manager must be documented and consistent with DOE delegation 
	authorities and the qualifications of the lower-level line manager. 
	Although the authority and responsibility for decision-making may be 
	delegated to a lower-level manager, the senior manager remains 
	accountable for the decisions made by subordinate managers. Key roles 
	and responsibilities of line managers are described in the following 
	sections:
	
	a.	Deputy Secretary.

		(1)	Serves as the senior manager responsible and accountable for all 
			project acquisitions.

		(2)	Exercises decision-making authority, including Critical Decisions 
			for all Major System Projects.

		(3)	Identifies special interest projects and ensures senior 
			executive-level quarterly reviews are provided for those projects.

		(4)	Approves disposition of projects and Performance Baseline changes 
			at the Secretarial Acquisition Executive approval level upon 
			Performance Baseline deviations.

		(5)	Serves as Chair for the Energy Systems Acquisition Advisory 
			Board.

		(6)	Approves site selection for facilities at new sites.

		(7)	Conducts quarterly project performance reviews for Major System 
			Projects, which may be delegated to the Under Secretaries.

	b.	Under Secretaries. 

		(1)	Receive Acquisition Executive authority from the Secretarial 
			Acquisition Executive, as appropriate.

		(2)	Delegate Acquisition Executive authority, as appropriate (refer 
			to Table 1).

		(3)	Exercise decision-making authority, including Critical Decisions, 
			functioning as the Acquisition Executive.

		(4)	Hold line accountability for applicable program and capital asset 
			project execution and implementation of policy.

		(5)	Hold accountability for project-related site environment, safety 
			and health, and safeguards and security.

		(6)	Serve as Chair and appoint members for Acquisition Advisory 
			Boards.

		(7)	Approve disposition of projects and Performance Baseline changes 
			below Secretarial Acquisition Executive approval level upon Performance 
			Baseline deviations (may be delegated to Program Secretarial Officers).

		(8)	Maintain a list of special interest projects and ensure senior 
			executive-level quarterly reviews are provided for those projects.

		(9)	Establish Project Management Support Offices or delegate this 
			responsibility to Program Secretarial Officers.

		(10)	Address and resolve issues between projects reporting to them.

		(11)	Conduct quarterly project performance reviews when serving as the 
			Acquisition Executive. These reviews may be delegated to the Program 
			Secretarial Officer.

	c.	Program Secretarial Officers and Deputy Administrators/Associate 
		Administrators for the National Nuclear Security Administration.

		(1)	Hold line accountability for applicable program and capital asset 
			project execution and implementation of policy.

		(2)	Hold accountability for project-related site environment, safety 
			and health, and safeguards and security.

		(3)	Approve Mission Need Statement documents and Acquisition Strategy 
			documents for all capital asset projects (cannot be delegated).

		(4)	Approve disposition of projects and Performance Baseline changes 
			below Secretarial Acquisition Executive approval level following 
			Performance Baseline deviations. If delegated, this authority cannot be 
			further delegated.

		(5)	Exercise decision-making authority, including Critical Decisions 
			when functioning as Acquisition Executive.

		(6)	Approve CD-0 for all projects with a Total Project Cost or 
			Environmental Management Total Project Cost less than $100M (cannot be 
			delegated).

		(7)	Delegate Acquisition Executive functions, as appropriate (refer 
			to Table 1).

		(8)	Nominates Federal Project Directors, when the Acquisition 
			Executive is above the Program Secretarial Officer, no later than CD-1 
			(can be delegated). The Federal Project Director appointment is subject 
			to the approval of the Acquisition Executive.

		(9)	Serve as Chair and appoint members for Acquisition Advisory 
			Boards.

		(10)	Direct Independent Project Reviews.

		(11)	Establish Project Management Support Offices when responsibility 
			is delegated or directed by the Under Secretaries.
			
		(12)	Ensures that safety is fully integrated into design and 
			construction for high-risk, high-hazard, and Hazard Category 1, 2, and 
			3 nuclear facilities.

	d.	Project Management Support Offices (when established).

		(1)	Provide independent oversight and report directly to the Under 
			Secretaries, or Program Secretarial Officer, as appropriate.

		(2)	Serve as the Secretariat for the Program Secretarial 
			Officer/National Nuclear Security Administration-level Advisory Board 
			functions.

		(3)	Coordinate quarterly performance reports.

		(4)	Perform Performance Baseline Validation Independent Project 
			Review and other Independent Project Reviews as required by the Program 
			Secretarial Officer. 

		(5)	Develop Program-specific implementing guidance, policies, and 
			procedures. 

		(6)	Collect, analyze, and disseminate lessons learned and “best 
			practices.”

		(7)	Coordinate with other DOE organizations and offices, including 
			the Office of Engineering and Construction Management, to ensure 
			effective and consistent implementation of project management policies 
			and directives.

		(8)	Provide assistance and oversight to line project management 
			organizations.

		(9)	Analyze project management execution issues.

		(10)	Actively assist senior management on issues related to project 
			management performance, including implementation of corrective actions.

		(11)	Provide support to the Federal Project Directors. 

		(12)	Validate the Performance Baseline for capital asset projects with 
			a Total Project Cost or Environmental Management Total Project Cost 
			greater than or equal to $20M and less than $100M.
			
	e.	Program Managers and Heads of Field Organizations. 

		(1)	Direct initial project planning and execution roles for projects 
			assigned by the Acquisition Executive.

		(2)	Initiate definition of mission need based on input from Sites, 
			Laboratories, and Program Offices.

		(3)	Establish the Integrated Project Team.

		(4)	Oversee development of project definition, technical scope, and 
			budget to support mission need.

		(5)	Initiate development of the Acquisition Strategy before CD-1 
			(during the period preceding designation of the Federal Project 
			Director).

		(6)	Perform functions as Acquisition Executive when so delegated.

		(7)	Develop project performance measures, and monitor and evaluate 
			project performance throughout the project’s life cycle.

		(8)	Allocate resources throughout the program.

		(9)	Oversee the project line-management organization and ensure the 
			line project teams have the necessary experience, expertise, and 
			training in design engineering, safety and security analysis, 
			construction, and testing.

		(10)	Serve as the Federal Project Director until the Federal Project 
			Director is appointed.

		(11)	Ensures that safety is fully integrated into design and 
			construction for high-risk, high-hazard, and Hazard Category 1, 2, and 
			3 nuclear facilities.

	f.	Acquisition Executives. 

		The following roles and responsibilities are for illustrative purposes, 
		and each designated Acquisition Executive is guided by the specific 
		limits of his/her delegated authority.
		
		(1)	Approve Critical Decisions (CD-0 cannot be delegated below the 
			Program Secretarial Officer level).

		(2)	Appoint and Chair Acquisition Advisory Boards to provide advice 
			and recommendations on key project decisions.

		(3)	Approve the appointment of the Federal Project Director.

		(4)	Designate the Design Authority at CD-1.

		(5)	Monitor the effectiveness of Federal Project Directors and their 
			support staff.

		(6)	Approve project changes in compliance with change control levels 
			identified in Project Execution Plans.

		(7)	Conduct monthly and quarterly project performance reviews.

		(8)	Ensures that safety is fully integrated into design and 
			construction for high-risk, high-hazard, and Hazard Category 1, 2, and 
			3 nuclear facilities.
			
	g.	Federal Project Director. 

		Successful performance of DOE projects depends on professional and 
		effective project management by the Federal Project Director. The 
		Federal Project Director is responsible and accountable to the 
		Acquisition Executive/Program Secretarial Officer or delegated 
		authority, as appropriate, for executing the project. 
		
		The Federal Project Director’s assigned project must meet cost, 
		schedule and performance targets unless circumstances beyond the 
		control of the Project direct result in cost overruns and/or delays. 
		Federal Project Directors must demonstrate initiative in incorporating 
		and managing an appropriate level of risk to ensure best value for the 
		government. In cases where significant cost overruns and/or delays 
		occur, the Federal Project Director alerts senior management in a 
		timely manner and takes appropriate steps to mitigate these cost 
		overruns or delays.

		Roles and responsibilities of the Federal Project Director’s team must 
		be clearly defined relative to the contractor management team. Further 
		guidance is provided in DOE M 413.3-1.
		
		(1)	Attains and maintains certification in concert with the 
			requirements outlined in DOE O 361.1A before they are delegated 
			authority to serve as a Federal Project Director.

		(2)	Plans, implements, and completes a project using a Systems 
			Engineering approach.

		(3)	Initiates development and implementation of key project 
			documentation (e.g., Project Execution Plan).

		(4)	Defines project cost, schedule, performance, and scope baselines.

		(5)	Is responsible for design, construction, environmental, safety, 
			security, health, and quality efforts performed comply with the 
			contract, public law, regulations, and Executive Orders.

		(6)	Is responsible for timely, reliable, and accurate integration of 
			contractor performance data into the project’s scheduling, accounting, 
			and performance measurement systems.

		(7)	Evaluates and verifies reported progress; makes projections of 
			progress and identifies trends.

		(8)	Serves as the single point of contact between Federal and 
			contractor staff for all matters relating to a project and its 
			performance.

		(9)	Serves as the Contracting Officer’s Representative, as determined 
			by the Contracting Officer.

		(10)	Leads the Integrated Project Team and provides broad program 
			guidance. Delegates appropriate decision-making authority to the 
			Integrated Project Team members. 

		(11)	Prepares and maintains the Integrated Project Team Charter and 
			operating guidance with Integrated Project Team support.

		(12)	Approves changes in compliance with the approved change control 
			process documented in the Project Execution Plan.

		(13)	Ensures that safety is fully integrated into design and 
			construction for high-risk, high-hazard, and Hazard Category 1, 2, and 
			3 nuclear facilities.

	h.	Departmental Staff and Support Offices. 

		Departmental Staff and Support Offices develop policy and related 
		implementing guidance, perform review functions, and provide advice and 
		recommendations to Department leadership. Key roles and 
		responsibilities of these offices regarding the acquisition of capital 
		assets follow.

	i.	Office of Environment, Health and Safety.

		(1)	Serves as a member of the Energy Systems Acquisition Advisory 
			Board.

		(2)	Advises the Deputy Secretary in his/her role as the Secretarial 
			Acquisition Executive on environmental and safety matters related to 
			all Critical Decision approvals.

		(3)	Serves on the Independent Project Review as a team member at the 
			request of the Secretarial Acquisition Executive, Program Secretarial 
			Officer, Program Manager, Operations/Field Office Manager, or Federal 
			Project Director.
	
		(4)	Participates on External Independent Reviews as an observer at 
			the request of the Office of Engineering and Construction Management.

		(5)	Participates in safety documentation and Quality Assurance 
			reviews for acquisition projects at the request of the Office of 
			Engineering and Construction Management and/or the Acquisition 
			Executive when considered appropriate.

		(6)	Participates in Operational Readiness Reviews or Readiness 
			Assessments at the request of the line organizations.

		(7)	Supports the Central Technical Authorities as requested.

j.	Office of the Chief Information Officer.

		(1)	Holds delegated Acquisition Executive authority over Departmental 
			Information Technology Projects between $5M < $100M.

		(2)	Develops and maintains Department-wide policy, requirements, and 
			guidance for Information Technology projects, including Information 
			Technology hardware, software and application, and capital assets.
			
		(3)	Advises and provides programmatic support to ensure that 
			Information Technology is acquired and information resources are 
			managed in accordance with all applicable statutory, regulatory, and 
			agency requirements.

		(4)	Provides Information Technology investment management process 
			assistance to Program Offices, field elements, and contractor 
			locations, as requested.

		(5)	Regularly collects process performance measurement information, 
			and prepares a summary report on the status and performance of 
			Information Technology investments.

		(6)	Establishes Enterprise Architecture policy and practice within 
			DOE to ensure the development and maintenance of a sound and integrated 
			Information Technology portfolio of investments that are aligned to the 
			strategic business goals of the Department.

	k.	Office of Engineering and Construction Management within the 
		Office of Management. 

		(1)	Serves as DOE’s principal point of contact relating to project 
			management.

		(2)	Develops policy, requirements, and guidance for the acquisition 
			of capital assets.

		(3)	Assist in the planning, programming, budgeting, and execution 
			process for the acquisition of capital assets in coordination with the 
			Program Secretarial Officers and Project Management Support Offices.

		(4)	Supports the Office of the Secretary, the Secretarial Acquisition 
			Executive, the Under Secretaries, and the Program Secretarial Officer 
			in the Critical Decision process; and oversight of the acquisition 
			management process.
	
		(5)	Serves as Secretariat for the Energy Systems Acquisition Advisory 
			Board.

		(6)	Serves as an Acquisition Advisory Board member for Non-Major 
			System Projects with a Total Project Cost or Environmental Management 
			Total Project Cost greater than or equal to $100M.

		(7)	Manages the Project Management Career Development Program.

		(8)	Manages the Earned Value Management System certification process.

		(9)	Reviews Acquisition Strategies for Major System Projects.

		(10)	Maintains a corporate project reporting capability.

		(11)	Establishes, maintains, and executes a corporate independent 
			review capability to provide an independent assessment and analysis of 
			project planning, execution, and performance.

		(12)	Validates the Performance Baseline for all capital asset projects 
			with a Total Project Cost or Environmental Management Total Project 
			Cost greater than or equal to $100M to permit inclusion in the DOE 
			annual budget.

	l.	Office of Program Analysis and Evaluation. 

		Reviews Mission Need Statements for all capital asset projects with a 
		Total Project Cost or Environmental Management Total Project Cost 
		greater than or equal to $100M, and makes a recommendation to Program 
		Secretarial Officer prior to CD-0.

	m.	Integrated Project Team. 

		(1)	Supports the Federal Project Director.

		(2)	Develops a project contracting strategy.

		(3)	Ensures project interfaces are identified, defined, and managed 
			to completion.

		(4)	Identifies, defines, and manages to completion the project 
			environmental, safety, health, security, and quality assurance 
			requirements.

		(5)	Identifies and defines appropriate and adequate project technical 
			scope, schedule, and cost parameters.

		(6)	Performs periodic reviews and assessments of project performance 
			and status against established performance parameters, baselines, 
			milestones, and deliverables.

		(7)	Plans and participates in project reviews, audits, and appraisals 
			as necessary.
			
		(8)	Reviews all Critical Decision packages and recommend 
			approval/disapproval.

		(9)	Reviews and comments on project deliverables (e.g., drawings, 
			specifications, procurement, and construction packages).

		(10)	Reviews change requests (as appropriate) and support Change 
			Control Boards as requested.

		(11)	Participates, as required, in Operational Readiness Reviews or 
			Readiness Assessments.

		(12)	Supports preparation, review, and approval of project completion 
			and closeout documentation.

		(13)	Ensures that safety is fully integrated into design and 
			construction for high-risk, high-hazard, and Hazard Category 1, 2, and 
			3 nuclear facilities.

	n.	Central Technical Authorities. 

		The Central Technical Authorities are responsible for maintaining 
		operational awareness, especially with respect to complex, high-hazard 
		nuclear operations, and ensuring the Department’s nuclear safety 
		policies and requirements are implemented adequately and properly. In 
		this context, it is important to recognize that the Central Technical 
		Authorities have responsibilities related to nuclear safety directives 
		that apply to projects. The overall roles and responsibilities of the 
		Central Technical Authorities include:

		(1)	Concur with the determination of the applicability of DOE 
			Directives involving nuclear safety included in contracts pursuant to 
			DEAR 48 CFR 970.5204-2(b).

		(2)	Concur with nuclear safety requirements included in contracts 
			pursuant to DEAR 48 CFR 970.5204-2.

		(3)	Concur with all exemptions to nuclear safety requirements in 
			contracts that were added to the contract pursuant to DEAR 48 CFR 
			970.5204-2.
			
		(4)	Recommend to the Assistant Secretary for Environment, Safety and 
			Health issues and proposed resolutions concerning DOE safety 
			requirements, concur in the adoption or revision of nuclear safety 
			requirements (including supplemental requirements), and provide 
			expectations and guidance for implementing nuclear safety requirements 
			for use by DOE employees and contractors.

o.	Chief of Defense Nuclear Safety and Chief of Nuclear Safety. 

	The Chiefs (and staff) are responsible for evaluating nuclear safety 
	issues and providing expert advice to the Central Technical Authorities 
	and other senior officials. For Hazard Category 1, 2, or 3 nuclear 
	facilities, the Chief:

		(1)	Participates as part of the Energy Systems Acquisition Advisory 
			Board, or similar advisory boards.

		(2)	Provides support to both the Central Technical Authorities and 
			Acquisition Executive regarding the effectiveness of efforts to 
			integrated safety into design at each of the Critical Decisions, and as 
			requested during other project reviews.

		(3)	Validates that integration of design and safety basis activities 
			include the use of a system engineering approach tailored to the 
			specific needs and requirements of the project.
			
		(4)	Determines that nuclear facilities have incorporated the concept 
			of defense-in-depth into the facility design process.

		(5)	Validates that Federal personnel assigned to the Integrated 
			Project Team as nuclear safety experts are appropriately qualified.

	p.	Energy Systems Acquisition Advisory Board. 

		The Energy Systems Acquisition Advisory Board advises the Secretarial 
		Acquisition Executive on Critical Decisions related to Major System 
		Projects, site selection, and Performance Baseline deviation 
		dispositions.

	q.	Energy Systems Acquisition Advisory Board Membership. 

		(1)	Secretarial Acquisition Executive as Chair

		(2)	Under Secretaries

		(3)	DOE General Counsel 

		(4)	Director of Management

		(5)	Chief Financial Officer

		(6)	Director of the Office of Engineering and Construction Management

		(7)	Assistant Secretary for Environment, Safety and Health

		(8)	Assistant Secretary for Environmental Management

		(9)	Director of the Office of Security and Safety Performance 
			Assurance

		(10)	Deputy Administrator for Defense Programs

		(11)	Director of the Office of Science

		(12)	Assistant Secretary for Nuclear Energy

		The Deputy Secretary may designate other Program Secretarial Officers 
		or functional staff as Energy Systems Acquisition Advisory Board 
		members (temporary or permanent) as needed.

	r.	Energy Systems Acquisition Advisory Board Secretariat. 

		The Energy Systems Acquisition Advisory Board Secretariat resides in 
		the Office of Engineering and Construction Management and provides 
		administrative and analytical support and recommendations to the Energy 
		Systems Acquisition Advisory Board.

	s.	Non-Major System Project Advisory Boards. 

		The designated Acquisition Executive will appoint an Advisory Board to 
		provide advice and recommendations on actions for projects that are not 
		designated as Major Systems. The designated Acquisition Executive is 
		the Chair of the Advisory Board. The Advisory Board replicates and 
		conducts identical functions to those performed by the Energy Systems 
		Acquisition Advisory Board. Members may be selected from within the 
		Acquisition Executive’s organization. However, at least one member from 
		an office not under the Acquisition Executive will be designated as a 
		contributing representative. The Office of Engineering and Construction 
		Management will provide a member to each Advisory Board for projects 
		with a Total Project Cost or Environmental Management Total Project 
		Cost greater than or equal to $100M. The Office of Engineering and 
		Construction Management will not be a Board member for projects with a 
		Total Project Cost or Environmental Management Total Project Cost less 
		than $100M, but may be invited to attend the Advisory Board meetings. 
		The implementing documentation and composition of each Advisory Board 
		along with meeting agendas and minutes will be provided to the Office 
		of Engineering and Construction Management.
		
3.	REFERENCES.

	a.	10 CFR 830, Subpart A, Quality Assurance Requirements.

	b.	10 CFR 830, Subpart B, Safety Basis Requirements.

	c.	10 CFR 830.206, Preliminary Documented Safety Analysis.

	d.	10 CFR 851, Worker Safety and Health Program.

	e.	29 CFR 1910.119, Process Safety Management of Highly Hazardous 
		Substances.

	f.	40 CFR 68, Chemical Accident Prevention Provisions.

	g.	ANSI-EIA-649, National Consensus Standard for Configuration 
		Management.

	h.	ANSI-EIA-748-A-1998, Earned Value Management Systems.

	i.	DEAR 48 CFR 970.5204-2, Integration of Environmental, Safety, and 
		Health into Work Planning and Execution.

	j.	DOE O 205.1, Department of Energy Cyber Security Management 
		Program, dated 03-21-03.

	k.	DOE P 413.1, Program and Project Management Policy for the 
		Planning, Programming, Budgeting, and Acquisition of Capital Assets, 
		dated 06-10-00.

	l.	DOE O 425.1C, Startup and Restart of Nuclear Facilities, dated 
		03-13-03.

	m.	DOE O 430.2A, Departmental Energy and Utilities Management, dated 
		04-15-02.

	n.	DOE O 451.1B, Chg 1, National Environmental Policy Act Compliance 
		Program, dated 09-28-01.

	o.	DOE P 470.1, Integrated Safeguards and Security Management, dated 
		05-08-01.

	p.	DOE P 450.4, Safety Management System Policy, dated 10-15-96.

	q.	DOE P 226.1, Department of Energy Oversight Policy, dated 06-10-
		05.

	r.	DOE O 414.1C, Quality Assurance, dated 06-17-05.

	s.	DOE O 420.1B, Facility Safety, dated 12-22-05.

	t.	DOE M 413.3-1, Program Management for the Acquisition of Capital 
		Assets, dated 03-28-03.

	u.	DOE M 470.4-1, Safeguards and Security Program Planning and 
		Management, dated 08-26-05.

	v.	DOE O 361.1A, Acquisition Career Development Program, dated 04-
		19-04.

	w.	DOE O 450.1, Chg 2, Environmental Protection Program, dated 12-
		07-05.
	
	x.	DOE-STD-1189-2006.

	y.	House Report 109-86, “Energy and Water Development Appropriations 
		Bill, 2006.”

	z.	OECM, Project Management Practices, Integrated Safety, Revision 
		E, June 2003.

	aa.	OMB Circular A-11, Part 7, Planning, Budgeting, Acquisition, and 
		Management of Capital Assets, dated June 2006; and Supplement to Part 
		7-Capital Programming Guide.

	bb.	OMB Circular A-123, Management’s Responsibility for Internal 
		Control, dated 12?21?04.

	cc.	OMB Circular A-127, Financial Management Systems, dated 07-23-93.
	
	dd.	OMB Circular A-130, Management of Federal Information Resources, 
		Transmittal Memorandum #4, dated 11-28-00.

4.	CONTACT. Questions concerning this Order should be directed to 
	the Office of Engineering and Construction Management, 202-586-1784.

BY ORDER OF THE SECRETARY OF ENERGY:
	CLAY SELL
	Deputy Secretary

DEPARTMENTAL ELEMENTS TO WHICH
DOE ORDER 413.3A IS APPLICABLE

Office of the Secretary
Departmental Representative to the Defense Nuclear Facilities Safety 
Board 
National Nuclear Security Administration 
Office of Chief Financial Officer 
Office of Chief Information Officer 
Office of Civilian Radioactive Waste Management 
Office of Congressional and Intergovernmental Affairs 
Office of Economic Impact and Diversity 
Office of Electricity Delivery and Energy Reliability 
Office of Energy Efficiency and Renewable Energy 
Office of Energy Information Administration
Office of Environment, Safety, and Health 
Office of Environmental Management 
Office of Fossil Energy 
Office of General Counsel 
Office of Hearings and Appeals 
Office of Human Capital Management 
Office of Inspector General 
Office of Intelligence and Counterintelligence
Office of Legacy Management 
Office of Management 
Office of Nuclear Energy, Science, and Technology 
Office of Policy and International Affairs 
Office of Public Affairs 
Office of Science
Office of Security and Safety Performance Assurance 
Secretary of Energy Advisory Board
Southeastern Power Administration
Southwestern Power Administration
Western Area Power Administration


CONTRACTOR REQUIREMENTS DOCUMENT

DOE ORDER 413.3A, Program and Project Management 
for the Acquisition of Capital Assets

This Contractor Requirements Document sets forth intended requirements 
to be applied to contractors responsible for performing program and 
project management of Department-owned facilities and for other 
contractors as determined by the Federal Project Director and 
Contracting Officer, in conjunction with the Federally-assigned 
Integrated Project Team members. Regardless of the performer of the 
work, the affected contractor is responsible for complying with the 
requirements of this Contractor Requirements Document as included in 
the contract. The contractor is responsible for flowing down Contractor 
Requirements Document requirements to subcontractors at any tier to the 
extent necessary to ensure contractor compliance.

The contractor’s project management system must satisfy the following 
requirements:

1.	The industry standard for Performance Management Systems, 
	described in ANSI/EIA-748-A-1998, must be implemented and self-
	certified on all projects with a Total Project Cost greater than $20M. 
	For projects not required to utilize an Earned Value Management System 
	(e.g., firm fixed-price contract projects), an alternative Performance 
	Management System must be described in the Project Execution Plan and 
	utilized. For projects with Total Project Cost equal to or greater than 
	$50M, the Earned Value Management System must be validated by the 
	Office of Engineering and Construction Management. It is to be used for 
	control and reporting of project performance as defined in the Project 
	Execution Plan and no later than CD-2.
	
2.	Cost and schedule performance, milestone status, and financial 
	status no later than CD-2 must be reported to DOE on a monthly basis 
	using DOE-approved work breakdown structure elements and data elements 
	for all projects with a Total Project Cost greater than or equal to 
	$20M, except firm fixed-priced contracts. The report must also include 
	variance analyses and corrective action plans that integrate cost, 
	schedule, and scope if variances exceed DOE-established reporting 
	thresholds. Analyses of cost and schedule trends, financial status, and 
	baseline change control activity, including the allocation of 
	management reserve, potential problems, and critical issues will also 
	be reported. Reporting by the contractor may be required earlier than 
	CD-2 as specified by the Contracting Officer.

3.	For project contracts to be awarded as subcontracts by the 
	contractor, the contractor must have a written Acquisition Plan that is 
	appropriate for the requirement and dollar value of each subcontract 
	and consistent with its contract’s provisions. The Acquisition Plan for 
	a project contract to be awarded by the contractor is to be developed 
	by a team of contractor employees including, at a minimum, the 
	prospective Project Manager and Contract Negotiator. The Acquisition 
	Plan must receive the concurrence of both the Federal Project Director 
	and the DOE Contracting Officer.

4.	Technical performance analyses and corrective action plans must 
	be reported to DOE for variances to the project baseline objectives 
	resulting from design reviews, component and system tests, and 
	simulations.
	
5.	A critical path schedule and a project master schedule must be 
	developed and maintained.

6.	Cost estimating must be an integral part of cost baseline 
	including life cycle cost development and maintenance, budget request 
	development, and estimates at completion.

7.	Project technical, cost, and schedule risks must be identified, 
	quantified, and mitigated throughout the life of the project. Risks 
	must be identified, evaluated, and mitigation strategies developed and 
	implemented.

8.	An integrated contractor technical, cost, and schedule baseline 
	must be developed and maintained using a contractor-level Change 
	Control Board.

9.	A configuration management process must be established that 
	controls changes to the physical configuration of project facilities, 
	structures, systems, and components in compliance with ANSI/EIA-649, 
	National Consensus Standard for Configuration Management. This process 
	must also ensure that the configuration is in agreement with the 
	performance objectives identified in the technical baseline and the 
	approved quality assurance plan.

10.	A Value Management/Engineering process must be used that 
	identifies high-cost project activities in order to realize a maximum 
	return on investment through the use of systems engineering tradeoffs 
	and functional analyses that identify alternate means of achieving the 
	same function at a lower life cycle cost.

11.	A quality assurance program must be developed and implemented for 
	the contract scope of work when the contractor’s requirements include 
	DOE O 414.1C, Quality Assurance or 10 CFR 830 Subpart A, Quality 
	Assurance Requirements (as applicable).
	
12.	An Integrated Safety Management system must be developed and 
	implemented for the contract scope of work when the contractor is 
	complying with the requirements of DEAR 48 CFR 970.5204-2, Integration 
	of Environmental, Safety and Health into Work Planning and Execution.

13.	Contractors performing design for projects must at a minimum 
	conduct a Preliminary and Final Design Review, in accordance with the 
	Project Execution Plan. For nuclear projects, the design review will 
	include a focus on safety and security systems. 

14.	High performance sustainable building principles must be applied 
	to the siting, design, construction, and commissioning of new 
	facilities and major renovations of existing facilities.
	
DEFINITIONS

1.	Acquisition Executive. The individual designated by the Secretary 
	of Energy to integrate and unify the management system for a program 
	portfolio of projects, and implement prescribed policies and practices.
	
2.	Acquisition Strategy. An acquisition strategy is a high-level 
	business and technical management approach designed to achieve project 
	objectives within specified resource constraints. It is the framework 
	for planning, organizing, staffing, controlling, and leading a project. 
	It provides a master schedule for activities essential for project 
	success, and for formulating functional strategies and plans.

3.	Capital Assets. Capital assets are land, structures, equipment, 
	intellectual property (e.g., software), and Information Technology used 
	by the Federal government and having an estimated useful life of two or 
	more years. Capital assets include environmental restoration 
	(decontamination and decommissioning) of land to make useful leasehold 
	improvements and land rights, and assets whose ownership is shared by 
	the Federal Government with other entities. Capital assets may be 
	acquired in different ways: purchase, construction, or manufacture; a 
	lease-purchase or other capital lease (regardless of whether title has 
	passed to the Federal Government); or exchange. This Order does not 
	apply to land, structures, equipment, intellectual property (e.g., 
	software), or Information Technology acquired by State and local 
	governments or other entities through Financial Assistance (i.e., DOE 
	grants and cooperative agreements), or to assets acquired under General 
	Plant Projects for maintaining infrastructure at a site.

4.	Conceptual Design. The concept for meeting a mission need. The 
	Conceptual Design process requires a mission need as an input. Concepts 
	for meeting the need are explored and alternatives considered to arrive 
	at a set of alternatives that are technically viable, affordable and 
	sustainable.

5.	Configuration Management. The technical and administrative 
	direction and surveillance actions taken to identify and document the 
	functional and physical characteristics of a configuration item; to 
	control changes to a configuration item and its characteristics; and to 
	record and report change processing and implementation status.
	
6.	Contingency. Contingency is the portion of the project budget 
	that is available for risk uncertainty within the project scope, but 
	outside the scope of the contract. Contingency is budget that is not 
	placed on the contract, and is included in the Total Project Cost.

7.	Construction Manager. The individual or firm responsible to DOE 
	for supervision and administration of a construction project to ensure 
	the construction contractor's compliance with construction project 
	requirements. 

8.	Contractor Requirements Document. A Contractor Requirements 
	Document is the DOE document that identifies the requirements that the 
	Prime Contractor’s project management system must satisfy (Attachment 
	2).

9.	Critical Decision. A formal determination made by the Secretarial 
	Acquisition Executive/Acquisition Executive at a specific point in a 
	project’s life cycle that allows the project to proceed to the next 
	phase or Critical Decision.
	
10.	Deviation. A deviation occurs when the current estimate of a 
	performance, technical, scope, schedule, or cost parameter is not 
	within the threshold values of the Performance Baseline for that 
	parameter. It is handled as a deviation, not through the normal change 
	control system.

11.	Directed Change. A change imposed on a project(s) that affects 
	the project’s baseline. Example of directed changes include, but are 
	not limited to (a) changes to approved budgets, or funding, and (b) 
	changes resulting from DOE policy directives and regulatory or 
	statutory requirements.

12.	Earned Value. Earned Value is the budgeted value of work actually 
	accomplished in a given time. Simply defined, Earned Value represents 
	the value of work accomplished during the period. 
	
13.	Earned Value Management. Earned Value Management is a program and 
	project management methodology of which organization, planning, 
	progressing, tracking, management control, reporting, and communication 
	are essential elements.

14.	External Independent Review. A project review conducted by 
	individuals outside DOE. The Office of Engineering and Construction 
	Management selects an appropriate contractor to perform these reviews.
	
15.	Final Design. Completion of the design effort and production of 
	all the approved design documentation necessary to permit procurement, 
	construction, testing, checkout, and turnover to proceed. Final design 
	occurs between Critical Decision-2 and -3.

16.	Independent Cost Estimate. A “bottoms-up” documented, independent 
	cost estimate that has the express purpose of serving as an analytical 
	tool to validate, crosscheck, or analyze cost estimates developed by 
	project proponents.

17.	Independent Cost Review. An essential project management tool 
	used to analyze and validate an estimate of project costs by 
	individuals having no direct responsibility for project performance.
	
18.	Independent Project Review. Independent Project Reviews are 
	important project management tools and serve to verify the project’s 
	mission, organization, development, processes, technical requirements, 
	baselines, progress, etc. Independent Project Reviews are performed by 
	reviewers from within or outside the Program, but having no association 
	with the project being reviewed. 

19.	Integrated Project Team. An Integrated Project Team is a cross-
	functional group of individuals organized for the specific purpose of 
	delivering a project to an external or internal customer.

20.	Integrated Safety Management. The application of the integrated 
	safety management system to a project or activity. The fundamental 
	premise of Integrated Safety Management is that accidents are 
	preventable through early and close attention to safety, design, and 
	operation, and with substantial stakeholder involvement in teams that 
	plan and execute the project, based on appropriate standards.

21.	Key Performance Parameters. A vital characteristic of a project 
	or facility mission. A characteristic, function, requirement, or design 
	basis, that if changed, would have a major impact on the facility or 
	system performance, scope, schedule, cost and/or risk, or the ability 
	of an interfacing project to meet its mission requirements. Thus, a Key 
	Performance Parameter may be a performance, design or interface 
	requirement. Parameters that are appropriate for Key Performance 
	Parameters are those that express performance in terms of accuracy, 
	capacity, throughput, quantity, processing rate, purity, or others that 
	define how well a system, facility or other project will perform.
	
22.	Life Cycle Costs. The sum total of the direct, indirect, 
	recurring, nonrecurring, and other related costs incurred or estimated 
	to be incurred in the design, development, production, operation, 
	maintenance, support, long-term stewardship (if applicable), and final 
	disposition of a project/system over its anticipated useful life span. 
	Where system or project planning anticipates use of existing sites or 
	facilities, restoration and refurbishment costs are included in the 
	life cycle costs.

23.	Line Item. An appropriation by Congress for a specific effort, 
	activity, or project.

24.	Long-Lead Procurement. Equipment or material that must be 
	procured well in advance of the need for the materials because of long 
	delivery times.

25.	Maintenance. Day-to-day work required to sustain property in a 
	condition suitable for its designated purposes, including preventive, 
	predictive, and corrective maintenance.

26.	Major System. A project with a Total Project Cost of greater than 
	or equal to $750M or an Environmental Management Total Project Cost of 
	$1B or designated by the Deputy Secretary.

27.	Management Reserve. An amount of the total contract budget 
	withheld for management control purposes by the contractor. Management 
	Reserve is not part of the Performance Measurement Baseline.

28.	Mission Need Statement. A concise document that details a mission 
	requirement the Department cannot meet through nonmaterial method. 
	
29.	Non-Major System. Any project with a Total Project Cost less than 
	$750M or an Environmental Management Total Project Cost less than $1B.

30.	Performance Baseline. The collective key performance, scope, 
	cost, and schedule parameters, which are defined for all projects. 
	Performance Baseline includes the entire project budget (total cost of 
	the project including contingency) and represents DOE’s commitment to 
	Congress.

31.	Performance Measurement Baseline. The Performance Measurement 
	Baseline is the baseline that encompasses all project work packages and 
	planning packages. The Performance Measurement Baseline provides a view 
	from the bottom-up where work packages are summed within the Work 
	Breakdown Structure. Management Reserve, contingency, profit, fee and 
	similar cost items separately identified in the contract are not part 
	of the Performance Measurement Baseline because no work is associated 
	with those budgets.

32.	Project. A unique effort that supports a program mission having 
	defined points for starting and ending, undertaken to create a product, 
	facility, or system and containing interdependent activities planned to 
	meet a common objective or mission. A project is a basic building block 
	(in relation to a program) that is individually planned, approved, and 
	managed. A project is not constrained to any specific element of the 
	budget structure (e.g., operating expense, plant or capital equipment). 
	Projects include planning and execution of construction, assembly, 
	renovation, modification, environmental restoration, decontamination 
	and decommissioning, large capital equipment, and technology 
	development activities. Work that does not include the above elements, 
	e.g., basic research, grants, ordinary repairs, maintenance, and 
	operation of facilities are not considered projects. However, these 
	activities can be managed as projects.

33.	Project Data Sheet. A generic term defining the document that 
	contains summary project data and the justification required to include 
	the entire project effort as a part of the Departmental budget.

34.	Project Engineering and Design. Design funds established for use 
	on preliminary design, which are Operating Expense funds. Typically, 
	Project Engineering and Design funds are used for preliminary and final 
	design and related activities for design-bid-build strategies, and for 
	preliminary design and related costs in design-build strategies.

35.	Risk Management. Effective risk management is an essential 
	element of every project. The DOE risk management concept is based on 
	the principles that risk management must be analytical, forward-
	looking, structured, informative, and continuous. Risk assessments 
	should be performed as early as possible in the project life cycle and 
	should identify critical technical, performance, schedule, and cost 
	risks. Once risks are identified, sound risk mitigation strategies and 
	actions should be developed and documented. 

36.	System Engineering. A proven, disciplined approach that supports 
	management in clearly defining the mission or problem; managing system 
	functions and requirements; identifying and managing risk; establishing 
	bases for informed decision-making; and, verifying products and 
	services meet customer needs. The goal of the System Engineering 
	process is to transform mission operational requirements into system 
	architecture, performance parameters, and design details. 

37.	Total Project Cost. DOE has traditionally identified 
	project costs in two categories: (1) Total Estimated Cost, and (2) 
	Other Project Cost. The sum of the Total Estimated Cost and Other 
	Project Costs make up the Total Project Cost. 

	·	Total Estimated Cost includes project costs incurred after CD-1 
		such as costs associated with the acquisition of land and land rights; 
		engineering, design, and inspection; direct and indirect 
		construction/fabrication; and the initial equipment necessary to place 
		the plant or installation in operation. Total Estimated Cost may be 
		funded as an operating or capital expense. 
	
	·	Other Project Costs include all project costs that are not 
		identified as Total Estimated Cost costs. Generally, Other Project 
		Costs are costs incurred during the Initiation and Definition Phases 
		for planning, conceptual design, research and development, and during 
		the Execution Phase for startup and operation. Other Project Costs are 
		always operating funds.

38.	Value Management. Value Management is an organized effort 
	directed at analyzing the functions of systems, equipment, facilities, 
	services, and supplies for achieving the essential functions at the 
	lowest life cycle cost consistent with required performance, quality, 
	reliability, and safety. Value Management encompasses Value 
	Engineering.

39.	Value Engineering. Value Engineering is a planned, detailed 
	review/evaluation of a project to identify alternative approaches to 
	providing the needed assets.

40.	Value Study. Value Study is an intensive review of requirements 
	and the development of alternatives by the use of appropriate value 
	techniques utilizing aspects of engineering, requirements analysis, the 
	behavioral sciences, creativity, economic analysis, and the scientific 
	method.

41.	Variance. A variance is a deviation from the approved scope, 
	cost, or schedule performance. Variances must be tracked and reported. 
	Variances should be mitigated through corrective actions and not 
	eliminated through baseline change control unless valid rationale can 
	be presented to justify a change in baseline. Baseline changes are 
	submitted for changes in technical, work scope, funding, or directed 
	changes.